4039 E BEMIS ST 90039

Certificate Information: 4039 E BEMIS ST 90039

Application / Permit
22014-10000-06297
Plan Check / Job No.
B22LA26273
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan MERGING TWO (E) SFD WITH NEW ADDITION AND STR. REMODEL TO ONE UNIT SFD ON THE LOT WITH ATT. (E) CARPORT.
Permit Issued
Issued on 4/28/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 MAHNAZ NOURHASHEMI
Corrections Issued 2/15/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 2/24/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 4/18/2023 MAHNAZ NOURHASHEMI
No Progress 4/18/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 4/20/2023 MAHNAZ NOURHASHEMI
Issued 4/28/2023 APPLICANT
CofO in Progress 3/18/2024 LILIANA PORTILLO
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 2/28/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 3/9/2023 CINDY QI
Stormwater Pollution Mitigatn Cleared 3/21/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 3/23/2023 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/30/2023 Approved HAMIK HARTOUNIAN
Pre-Inspection 7/12/2023 Partial Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/19/2023 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 7/25/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 9/7/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/22/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/13/2023 Corrections Issued SCOTT FINNILA
HVAC-Rough 10/13/2023 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 10/17/2023 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 10/17/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/25/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/25/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/25/2023 Approved HAMIK HARTOUNIAN
Insulation 10/31/2023 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/31/2023 Partial Approval HAMIK HARTOUNIAN
Shower Pan 11/3/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 11/7/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/9/2023 Approved HAMIK HARTOUNIAN
Insulation 11/9/2023 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 11/17/2023 Approved JOSH MEISTER
Final 2/15/2024 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 2/15/2024 Approved LILIANA PORTILLO
Final 2/26/2024 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/15/2024 Approved LILIANA PORTILLO
Final 3/15/2024 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 3/15/2024 Approved LILIANA PORTILLO
PLUMBING-Final 3/15/2024 Approved LILIANA PORTILLO