4039 E BEMIS ST 90039
Certificate Information: 4039 E BEMIS ST 90039
- Application / Permit
- 22014-10000-06297
- Plan Check / Job No.
- B22LA26273
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan MERGING TWO (E) SFD WITH NEW ADDITION AND STR. REMODEL TO ONE UNIT SFD ON THE LOT WITH ATT. (E) CARPORT.
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 2/15/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/24/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 4/18/2023 | MAHNAZ NOURHASHEMI |
| No Progress | 4/18/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/20/2023 | MAHNAZ NOURHASHEMI |
| Issued | 4/28/2023 | APPLICANT |
| CofO in Progress | 3/18/2024 | LILIANA PORTILLO |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 2/28/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | CINDY QI |
| Stormwater Pollution Mitigatn | Cleared | 3/21/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/23/2023 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2023 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/12/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/19/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/25/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/7/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/13/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 10/13/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/17/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/17/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/25/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/25/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/25/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 10/31/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/31/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 11/3/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 11/7/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/9/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/17/2023 | Approved | JOSH MEISTER |
| Final | 2/15/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 2/15/2024 | Approved | LILIANA PORTILLO |
| Final | 2/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/15/2024 | Approved | LILIANA PORTILLO |
| Final | 3/15/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 3/15/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/15/2024 | Approved | LILIANA PORTILLO |