1950 S BUCKINGHAM ROAD 90016
Certificate Information: 1950 S BUCKINGHAM ROAD 90016
- Application / Permit
- 22014-10000-06290
- Plan Check / Job No.
- B22LA26268
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add addition and major remodel to existing 2 story SFD. Add new front porch , rear deck with roof , and interior and exterior renovation
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Current Status
- Issued on 9/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 3/14/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 3/28/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 5/3/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 5/23/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 6/13/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 6/28/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 8/1/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 8/25/2023 | HOOMAN HAJIZADEH |
| Issued | 9/13/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/17/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 8/18/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | CELINA MORENO |
Contact Information
| Contractor | Consma Inc; Lic. No.: 951561-B | , |
| Engineer | Chang,, Yeh; Lic. No.: S6868 | 168 S SIERRA MADRE BLVD 109 PASADENA, CA 91107 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/10/2023 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 10/16/2023 | Approved | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 10/23/2023 | Approved | CALEB MEISTER |
| Deputy Drilled-In Anchors | 11/1/2023 | Conditional Approval | DAVID FEILER |
| Special/Order Compliance | 2/6/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/5/2024 | Partial Approval | JUSTIN HAWLEY |
| Pre-Inspection | 3/28/2024 | Partial Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 6/7/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/15/2024 | Corrections Issued | JUSTIN HAWLEY |
| Special/Order Compliance | 8/15/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |