400 S SALTAIR AVE 90049

Certificate Information: 400 S SALTAIR AVE 90049

Application / Permit
22014-10000-06289
Plan Check / Job No.
B22LA26267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. interior remodel and addition to existing SFD.
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 YASHAR EMAMI
Corrections Issued 1/21/2023 YASHAR EMAMI
Quality Review Completed 2/2/2023 KAVIAN REFAHI
Plan Check Approved 2/27/2023 YASHAR EMAMI
Issued 2/28/2023 APPLICANT
CofO in Progress 10/30/2024 JESUS RODRIGUEZ
Permit Finaled 10/30/2024 RICHARD STEINBACH
CofO Issued 10/30/2024 RICHARD STEINBACH
Permit Finaled 10/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/6/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 2/6/2023 JENSON LEE
ZA Case Cleared 2/8/2023 MAXFIELD VERMY
ZA Case Cleared 2/8/2023 MAXFIELD VERMY
ZA Case Cleared 2/8/2023 MAXFIELD VERMY
ZA Case Cleared 2/8/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 2/9/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240
Engineer Carrillo,, Jesus Eduardo; Lic. No.: NA77737       ,

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/1/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/15/2023 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 5/16/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/22/2023 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/24/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 5/25/2023 No Access for Inspection KENNETH NAGLE
Deputy Drilled-In Anchors 6/20/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval OGANES TARAKHCHYAN
Insulation 6/22/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 6/29/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 7/3/2023 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 7/13/2023 Partial Approval OGANES TARAKHCHYAN
Wood Frame 8/7/2023 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 9/7/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 10/4/2023 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/19/2023 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/14/2023 Approved KENNETH NAGLE
PLUMBING-Rough 11/30/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 12/4/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/4/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/14/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/14/2023 Approved ARAM AVEDISIAN
Green Building Rough 12/14/2023 Approved ARAM AVEDISIAN
Insulation 12/21/2023 Approved ARAM AVEDISIAN
Drywall Nailing 1/2/2024 Approved KEVIN SARGSYAN
Shower Pan 1/19/2024 Approved KATHRYN BUTTERWORTH
Final 10/11/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/11/2024 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 10/11/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 10/18/2024 Approved JESUS RODRIGUEZ
Final 10/18/2024 Partial Approval JESUS RODRIGUEZ
Green Building Final 10/18/2024 Approved JESUS RODRIGUEZ
HVAC-Final 10/18/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 10/18/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 10/18/2024 Approved JESUS RODRIGUEZ
Final 10/28/2024 OK to Issue CofO JESUS RODRIGUEZ