2014 W ESTES ROAD 90041

Certificate Information: 2014 W ESTES ROAD 90041

Application / Permit
22014-10000-06284
Plan Check / Job No.
B22LA26263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO-STORY ADDITION TO EX. SFD. REMODEL THROUGHOUT. NEW PROPOSED DECK. WORK PER ENGINEER. AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED.
Permit Issued
Issued on 8/7/2023
Issuing Office
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 ROSENDO MEDINA
Corrections Issued 1/19/2023 ROSENDO MEDINA
Quality Review Completed 1/23/2023 STEVEN KIM
Applicant returned to address corrections 3/7/2023 ROSENDO MEDINA
Applicant returned to address corrections 6/22/2023 ROSENDO MEDINA
Applicant returned to address corrections 7/11/2023 ROSENDO MEDINA
Plan Check Approved 8/2/2023 ROSENDO MEDINA
Issued 8/7/2023 APPLICANT
CofO in Progress 2/21/2025 BRENDAN MORELLI
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/23/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 1/23/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 1/23/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 1/23/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/23/2023 TREVOR QUAN
Sewer availability Cleared 1/23/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 1/31/2023 THAN WIN
Distance to fire station Cleared 2/17/2023 KURT CORRAL
Hydrant and Access approval Cleared 2/17/2023 KURT CORRAL
Low Impact Development Cleared 2/23/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 2/23/2023 TREVOR QUAN
GPI Written Notices Cleared 3/14/2023 ROSENDO MEDINA
Grading Pre-Inspection Cleared 3/14/2023 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/4/2023 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 1/10/2024 Conditional Approval CRAIG VAUGHAN
Deputy Wood Construction 1/11/2024 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 1/11/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/12/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 1/18/2024 Partial Approval CRAIG VAUGHAN
Underground Mechanical 1/18/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 1/26/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/26/2024 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval CRAIG VAUGHAN
Green Building Rough 1/26/2024 Approved CRAIG VAUGHAN
HVAC-Rough 1/26/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/26/2024 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 1/26/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/7/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 2/7/2024 Approved ROY SPAULDING
HVAC-Rough 2/7/2024 Partial Approval ROY SPAULDING
PLUMBING-Rough 2/7/2024 Approved ROY SPAULDING
HVAC-Rough 2/13/2024 Approved CRAIG VAUGHAN
Insulation 2/13/2024 Approved CRAIG VAUGHAN
Drywall Nailing 2/20/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 2/22/2024 Approved CHARLES BOGHOSKHAN
Final 4/23/2024 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/23/2024 Approved CRAIG VAUGHAN
Green Building Final 4/23/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 4/23/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 7/31/2024 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 7/31/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 9/18/2024 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 9/18/2024 SGSOV No Gas ROY SPAULDING
Smoke Detectors 9/18/2024 Not Ready for Inspection ROY SPAULDING
Final 10/24/2024 Corrections Issued ROY SPAULDING
Smoke Detectors 10/24/2024 Not Ready for Inspection ROY SPAULDING
Final 2/3/2025 Corrections Issued BRENDAN MORELLI
Smoke Detectors 2/3/2025 Corrections Issued BRENDAN MORELLI
Final 2/20/2025 OK to Issue CofO BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 2/20/2025 Approved BRENDAN MORELLI