3710 N DOVER PL 90039

Certificate Information: 3710 N DOVER PL 90039

Application / Permit
22014-10000-06261
Plan Check / Job No.
B22LA26096
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN (E) TWO CAR GARAGE INTO A SINGLE STORY ADU PER CA GOVERNMENT CODE SEC 65852.2(E)(1)(A) WITH ADDITION AND (N) DRIVEWAY
Permit Issued
Issued on 5/1/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2022 APPLICANT
Assigned to Plan Check Engineer 12/27/2022 YAQUB MIRZA
Corrections Issued 12/28/2022 YAQUB MIRZA
Building Plans Picked Up 12/29/2022 APPLICANT
Plan Check Approved 1/10/2023 VICTOR CHEN
Issued 5/1/2023 APPLICANT
CofO in Progress 12/15/2023 HAMIK HARTOUNIAN
No Progress 12/18/2023 SCOTT FINNILA
CofO in Progress 1/5/2024 HAMIK HARTOUNIAN
Permit Finaled 1/11/2024 DEROLD HAUFF
CofO Issued 1/11/2024 DEROLD HAUFF
Permit Finaled 1/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/3/2023 TREVOR QUAN
Permit Cleared 1/3/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 1/3/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/4/2023 TREVOR QUAN
Sewer availability Cleared 1/4/2023 TREVOR QUAN

Contact Information

Contractor Hollywood Upgrade Construction Corp; Lic. No.: 1092628-B 842 W GAGE AVENUE      LOS ANGELES, CA 90044
Engineer Strege,, Bryan Michael; Lic. No.: S7045 1048 IRVINE AVE STE 1087      NEWPORT BEACH, CA 92660

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/8/2023 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/8/2023 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 5/8/2023 Corrections Issued JOSEPH MCGARRY
Underground Mechanical 5/11/2023 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/17/2023 Partial Approval JOSEPH MCGARRY
Sewer 5/17/2023 Approved JOSEPH MCGARRY
Underground Mechanical 5/17/2023 Partial Approval JOSEPH MCGARRY
Underground Mechanical 5/19/2023 Partial Approval JOSEPH MCGARRY
Gas Test 5/24/2023 Partial Approval JOSEPH MCGARRY
Underground Mechanical 5/24/2023 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/13/2023 Partial Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 6/13/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 No Access for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/12/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/12/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 7/12/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/12/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/20/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/20/2023 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/20/2023 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/20/2023 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 7/25/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/31/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/31/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 7/31/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/31/2023 Approved HAMIK HARTOUNIAN
Insulation 7/31/2023 Approved HAMIK HARTOUNIAN
Insulation 8/2/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 8/4/2023 Approved JOSH MEISTER
Shower Pan 8/21/2023 No Access for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/28/2023 Conditional Approval HAMIK HARTOUNIAN
Shower Pan 8/28/2023 Conditional Approval HAMIK HARTOUNIAN
Final 11/13/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/13/2023 Approved HAMIK HARTOUNIAN
Green Building Final 11/13/2023 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 11/13/2023 Approved HAMIK HARTOUNIAN
Final 11/22/2023 Corrections Issued BRENDAN MORELLI
Green Building Final 11/22/2023 Not Ready for Inspection BRENDAN MORELLI
Final 11/28/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 11/28/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 11/28/2023 Approved HAMIK HARTOUNIAN
Final 12/11/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 12/11/2023 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 12/11/2023 Approved HAMIK HARTOUNIAN
Final 12/15/2023 OK to Issue CofO HAMIK HARTOUNIAN