2802 1/2 W ANGUS ST 90039
Certificate Information: 2802 1/2 W ANGUS ST 90039
- Application / Permit
- 22014-10000-06260
- Plan Check / Job No.
- B22LA26094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) detached Garage with addition into Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | VICTOR CHEN |
| Corrections Issued | 1/3/2023 | VICTOR CHEN |
| Building Plans Picked Up | 1/10/2023 | APPLICANT |
| Applicant returned to address corrections | 7/10/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 7/11/2023 | MICHAEL LANZONE |
| Issued | 12/8/2023 | APPLICANT |
| CofO in Progress | 12/27/2024 | ENRIQUE MIRELES |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| CofO Issued | 12/29/2024 | DEROLD HAUFF |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/10/2023 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 1/18/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2023 | JEANIE LAM |
| Sewer availability | Cleared | 1/19/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 4/15/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/30/2023 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/5/2023 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 7/10/2023 | JONATHAN HOM |
| Hold | Cleared | 2/20/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Hades Construction; Lic. No.: 1047035-B | 8954 RESEDA BLVD #202 NORTHRIDGE, CA 91324 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/22/2024 | Approved | ENRIQUE MIRELES |
| Sewer | 3/13/2024 | Approved | ENRIQUE MIRELES |
| Sewer | 3/21/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/22/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/5/2024 | Corrections Issued | JEFFREY MEAD |
| Underground Mechanical | 4/5/2024 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 4/12/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/19/2024 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/23/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/9/2024 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 5/9/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/21/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/21/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 5/23/2024 | Corrections Issued | JEFFREY MEAD |
| Insulation | 6/3/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/11/2024 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 6/17/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/26/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 8/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 8/29/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 9/11/2024 | Approved | BRENDAN MORELLI |
| HVAC-Final | 9/11/2024 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 9/11/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/26/2024 | Approved | ENRIQUE MIRELES |
| Final | 9/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 9/26/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 12/5/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 12/5/2024 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/5/2024 | Partial Approval | ENRIQUE MIRELES |
| Final | 12/23/2024 | OK to Issue CofO | ENRIQUE MIRELES |
| Smoke Detectors | 12/23/2024 | Approved | ENRIQUE MIRELES |