Deputy Drilled-In Anchors
|
12/12/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
12/14/2023
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
12/21/2023
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Deputy Drilled-In Anchors
|
1/25/2024
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
1/30/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
2/15/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Deputy Reinf. Concrete
|
2/20/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
3/4/2024
|
No Access for Inspection
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
3/13/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Deputy Reinf. Concrete
|
3/14/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
3/28/2024
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
4/2/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
4/22/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
4/23/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
4/25/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Deputy Drilled-In Anchors
|
6/20/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
7/12/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
7/15/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
7/16/2024
|
No Access for Inspection
|
SEAN HAUPT
|
|
Green Building Rough
|
7/16/2024
|
No Access for Inspection
|
SEAN HAUPT
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/19/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Deputy Drilled-In Anchors
|
7/30/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
8/21/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Other (see comments)
|
8/21/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/26/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
8/29/2024
|
Approved
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
9/9/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
9/23/2024
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/4/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/25/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Green Building Rough
|
10/25/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
11/5/2024
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
12/2/2024
|
Approved
|
STEPHANIE SWANSON
|
|
Deputy Drilled-In Anchors
|
12/3/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Green Building Rough
|
12/6/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
PLUMBING-Rough
|
12/6/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
12/19/2024
|
Approved
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Green Building Rough
|
12/19/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/23/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Green Building Rough
|
12/23/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
1/6/2025
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/8/2025
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Green Building Rough
|
1/8/2025
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/28/2025
|
Partial Approval
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Rough
|
4/8/2025
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
HVAC-Rough
|
4/8/2025
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
PLUMBING-Rough
|
4/8/2025
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Rough
|
4/15/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
4/17/2025
|
Not Ready for Inspection
|
DANIEL VERA
|
|
Shower Pan
|
4/17/2025
|
Approved
|
DANIEL VERA
|
|
Interior/Exterior Lathing
|
5/27/2025
|
Approved
|
STEPHANIE SWANSON
|
|
Underground Mechanical
|
6/4/2025
|
Corrections Issued
|
DANIEL VERA
|
|
Underground Mechanical
|
7/10/2025
|
Approved
|
DANIEL VERA
|
|
Interior/Exterior Lathing
|
7/22/2025
|
Approved
|
DANIEL VERA
|
|
ELECTRICAL-Rough
|
7/24/2025
|
Partial Approval
|
DANIEL VERA
|
|
BUILDING-Rough-Frame
|
7/25/2025
|
Approved
|
DANIEL VERA
|
|
Green Building Rough
|
7/25/2025
|
Approved
|
DANIEL VERA
|
|
HVAC-Final
|
7/25/2025
|
Corrections Issued
|
DANIEL VERA
|
|
HVAC-Rough
|
7/25/2025
|
Partial Approval
|
DANIEL VERA
|
|
Insulation
|
8/6/2025
|
Approved
|
DANIEL VERA
|
|
Drywall Nailing
|
8/19/2025
|
Approved
|
DANIEL VERA
|
|
Underground Mechanical
|
8/19/2025
|
Approved
|
DANIEL VERA
|
|
ELECTRICAL-Rough
|
9/22/2025
|
Not Ready for Inspection
|
DANIEL VERA
|
|
Pre-Inspection
|
10/28/2025
|
Approved
|
DANIEL VERA
|
|
ELECTRICAL-Final
|
2/18/2026
|
Approved
|
RYAN SALAZAR
|
|
HVAC-Final
|
2/19/2026
|
Approved
|
EVAN COOPER
|
|
PLUMBING-Final
|
2/20/2026
|
Approved
|
RYAN SALAZAR
|
|
Final
|
3/17/2026
|
Corrections Issued
|
RYAN SALAZAR
|
|
Footing/Foundation/Slab
|
3/17/2026
|
Approved
|
RYAN SALAZAR
|
|
Green Building Final
|
3/17/2026
|
Approved
|
RYAN SALAZAR
|
|
SGSOV-Seismic Gas S/O Valve
|
3/17/2026
|
SGSOV Approved
|
RYAN SALAZAR
|
|
Smoke Detectors
|
3/17/2026
|
Approved
|
RYAN SALAZAR
|
|
Final
|
4/1/2026
|
OK to Issue CofO
|
RYAN SALAZAR
|