2554 S PROSSER AVE 90064

Certificate Information: 2554 S PROSSER AVE 90064

Application / Permit
22014-10000-06220
Plan Check / Job No.
B22LA25927
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 2ND FLOOR ADDITION TO (E) 1-STORY SFD WITH INT. & EXT. STRUCTURAL REMODEL
Permit Issued
Issued on 4/27/2023
Issuing Office
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 MAHNAZ NOURHASHEMI
Corrections Issued 2/4/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 2/10/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 4/26/2023 MAHNAZ NOURHASHEMI
Issued 4/27/2023 APPLICANT
CofO in Progress 8/9/2024 KIRK SANDERS
Permit Finaled 8/26/2024 RICHARD STEINBACH
CofO Issued 8/26/2024 RICHARD STEINBACH
Permit Finaled 8/26/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/15/2023 JENSON LEE
Roof/Waste drainage to street Cleared 2/15/2023 JENSON LEE
Sewer availability Cleared 2/15/2023 JENSON LEE
Specific Plan Cleared 2/15/2023 KYLE WINSTON
ZI Cleared 2/15/2023 KYLE WINSTON
Specific Plan Cleared 2/21/2023 FREDDY GARCIA
Stormwater Pollution Mitigatn Cleared 4/6/2023 LUIS LUVANO
GPI Written Notices Cleared 4/27/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Alexander,, Andy; Lic. No.: NA84086       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/20/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 6/20/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 8/7/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/23/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 10/23/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 10/23/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 10/23/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 10/23/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 12/7/2023 Approved MICHAEL PELHAM
ELECTRICAL-Rough 12/7/2023 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved MICHAEL PELHAM
HVAC-Rough 12/7/2023 Not Ready for Inspection MICHAEL PELHAM
Insulation 12/7/2023 Approved MICHAEL PELHAM
PLUMBING-Rough 12/7/2023 Approved MICHAEL PELHAM
Verify Sprinkler Sign Off 12/7/2023 Approved MICHAEL PELHAM
Interior/Exterior Lathing 12/18/2023 Partial Approval OGANES TARAKHCHYAN
Shower Pan 12/18/2023 Corrections Issued OGANES TARAKHCHYAN
Drywall Nailing 12/27/2023 Approved OGANES TARAKHCHYAN
Shower Pan 1/3/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 1/4/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 2/6/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/6/2024 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/8/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 6/5/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 6/5/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 6/17/2024 Corrections Issued HERBERT GIRON
Gas Test 6/17/2024 Approved HERBERT GIRON
PLUMBING-Final 6/17/2024 Approved HERBERT GIRON
ELECTRICAL-Final 6/21/2024 Approved CHRISTOPHER WILSON
HVAC-Final 6/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 7/9/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Final 7/9/2024 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 7/9/2024 Approved STEPHANIE SWANSON
Final 7/29/2024 Corrections Issued KIRK SANDERS
HVAC-Final 7/29/2024 Approved KIRK SANDERS
Final 8/8/2024 OK to Issue CofO KIRK SANDERS