2554 S PROSSER AVE 90064
Certificate Information: 2554 S PROSSER AVE 90064
- Application / Permit
- 22014-10000-06220
- Plan Check / Job No.
- B22LA25927
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 2ND FLOOR ADDITION TO (E) 1-STORY SFD WITH INT. & EXT. STRUCTURAL REMODEL
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 2/4/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/10/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 4/26/2023 | MAHNAZ NOURHASHEMI |
| Issued | 4/27/2023 | APPLICANT |
| CofO in Progress | 8/9/2024 | KIRK SANDERS |
| Permit Finaled | 8/26/2024 | RICHARD STEINBACH |
| CofO Issued | 8/26/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/26/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 2/15/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/15/2023 | JENSON LEE |
| Specific Plan | Cleared | 2/15/2023 | KYLE WINSTON |
| ZI | Cleared | 2/15/2023 | KYLE WINSTON |
| Specific Plan | Cleared | 2/21/2023 | FREDDY GARCIA |
| Stormwater Pollution Mitigatn | Cleared | 4/6/2023 | LUIS LUVANO |
| GPI Written Notices | Cleared | 4/27/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy; Lic. No.: NA84086 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/20/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| Wood Frame | 8/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/23/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 10/23/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 10/23/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 10/23/2023 | Corrections Issued | CLAYTON GRAHAM |
| Wood Frame | 10/23/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Rough | 12/7/2023 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 12/7/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Insulation | 12/7/2023 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 12/7/2023 | Approved | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 12/7/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 12/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 12/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/27/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 1/3/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/4/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/6/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/6/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/5/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 6/5/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 6/17/2024 | Corrections Issued | HERBERT GIRON |
| Gas Test | 6/17/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 6/17/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/21/2024 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 6/21/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 7/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 7/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 7/9/2024 | Approved | STEPHANIE SWANSON |
| Final | 7/29/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 7/29/2024 | Approved | KIRK SANDERS |
| Final | 8/8/2024 | OK to Issue CofO | KIRK SANDERS |