24419 S DEEPWATER AVE 90744

Certificate Information: 24419 S DEEPWATER AVE 90744

Application / Permit
22014-10000-06196
Plan Check / Job No.
B22LA25853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED GARAGE CONVERSION INTO A.D.U. PER ORDINANCE AT REAR OF LOT. INCLUDES 2-STORY ADDITIONS.
Permit Issued
Issued on 7/18/2024
Issuing Office
San Pedro
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 LAWRENCE QUIRANTE
Corrections Issued 1/27/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 1/30/2023 APPLICANT
Plan Check Approved 5/16/2023 WEIJIAN HUANG
Issued 7/18/2024 APPLICANT
CofO in Progress 1/20/2026 JOSEPH MCGARRY
Permit Finaled 1/20/2026 ANSON MAGLASANG
CofO Issued 1/20/2026 ANSON MAGLASANG
Permit Finaled 1/20/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/17/2023 KHAING AYE
Roof/Waste drainage to street Cleared 3/1/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 3/17/2023 KHAING AYE
Miscellaneous Cleared 5/12/2023 KHAING AYE
Sewer availability Cleared 5/12/2023 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2025 Approved EUGENE CASSIDY
Deputy Drilled-In Anchors 2/3/2025 Conditional Approval ANSON MAGLASANG
PLUMBING-Rough 2/3/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 2/7/2025 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 2/7/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 2/7/2025 Approved EUGENE CASSIDY
Footing/Foundation/Slab 2/11/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 3/25/2025 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 3/25/2025 Approved EUGENE CASSIDY
Green Building Rough 3/25/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 3/25/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 4/10/2025 Partial Approval EUGENE CASSIDY
Wood Frame 4/10/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 6/5/2025 Approved EUGENE CASSIDY
HVAC-Rough 6/5/2025 Approved EUGENE CASSIDY
Insulation 6/24/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 6/24/2025 Approved EUGENE CASSIDY
Drywall Nailing 6/27/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/24/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/6/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Not Ready EUGENE CASSIDY
BUILDING-Rough-Frame 12/26/2025 Approved EUGENE CASSIDY
Final 12/26/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 12/26/2025 Approved EUGENE CASSIDY
Green Building Rough 12/26/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/26/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 12/26/2025 Approved EUGENE CASSIDY
Final 1/16/2026 OK to Issue CofO JOSEPH MCGARRY