9612 S GRAPE ST 90002

Certificate Information: 9612 S GRAPE ST 90002

Application / Permit
22014-10000-06183
Plan Check / Job No.
B22LA25817
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE (n) 2-STORY SFD ;FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 6/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 MOHAMMAD ESMAILI
Corrections Issued 1/8/2023 MOHAMMAD ESMAILI
Quality Review Completed 1/12/2023 OMID HEDAYAT
Building Plans Picked Up 2/3/2023 APPLICANT
Plan Check Approved 6/12/2023 MOHAMMAD ESMAILI
Issued 6/20/2023 APPLICANT
CofO in Progress 4/15/2024 BEN MOLSTAD
Permit Finaled 4/25/2024 ANSON MAGLASANG
CofO Issued 4/25/2024 ANSON MAGLASANG
Permit Finaled 4/25/2024 ANSON MAGLASANG

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/25/2023 RUEL COLE
Address approval Cleared 4/3/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/3/2023 JEANIE LAM
Sewer availability Cleared 4/17/2023 JEANIE LAM
Low Impact Development Cleared 5/9/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/15/2023 JEANIE LAM

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2023 Approved JOHN KLARIN
PLUMBING-Rough 7/17/2023 Partial Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/25/2023 Approved JOHN KLARIN
Drywall Nailing 8/10/2023 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 9/12/2023 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval JOHN KLARIN
Green Building Rough 9/12/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 9/12/2023 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 10/31/2023 Partial Approval JAMES CHAVEZ
Rough-Elec/Plmb/HVAC 10/31/2023 Approved JAMES CHAVEZ
Insulation 11/6/2023 Corrections Issued JOHN KLARIN
Insulation 11/9/2023 Approved JOHN KLARIN
Drywall Nailing 11/27/2023 Approved JOHN KLARIN
Sewer 1/12/2024 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/29/2024 Partial Approval BEN MOLSTAD
Final 3/29/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 3/29/2024 Approved BEN MOLSTAD
Green Building Final 3/29/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved BEN MOLSTAD
Service/Power Release 3/29/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 3/29/2024 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 3/29/2024 Approved BEN MOLSTAD
Final 4/3/2024 Not Ready for Inspection BEN MOLSTAD
Pre-Inspection 4/3/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 4/12/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 4/12/2024 Approved BEN MOLSTAD
Final 4/12/2024 OK to Issue CofO BEN MOLSTAD
HVAC-Final 4/12/2024 Approved BEN MOLSTAD
PLUMBING-Final 4/12/2024 Approved BEN MOLSTAD
Service/Power Release 4/12/2024 Approved BEN MOLSTAD