9612 S GRAPE ST 90002
Certificate Information: 9612 S GRAPE ST 90002
- Application / Permit
- 22014-10000-06183
- Plan Check / Job No.
- B22LA25817
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE (n) 2-STORY SFD ;FIRE SPRINKLER NFPA 13D
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/8/2023 | MOHAMMAD ESMAILI |
| Quality Review Completed | 1/12/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 2/3/2023 | APPLICANT |
| Plan Check Approved | 6/12/2023 | MOHAMMAD ESMAILI |
| Issued | 6/20/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | BEN MOLSTAD |
| Permit Finaled | 4/25/2024 | ANSON MAGLASANG |
| CofO Issued | 4/25/2024 | ANSON MAGLASANG |
| Permit Finaled | 4/25/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/25/2023 | RUEL COLE |
| Address approval | Cleared | 4/3/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | JEANIE LAM |
| Sewer availability | Cleared | 4/17/2023 | JEANIE LAM |
| Low Impact Development | Cleared | 5/9/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/15/2023 | JEANIE LAM |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/17/2023 | Partial Approval | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/25/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/10/2023 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/12/2023 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 9/12/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/12/2023 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 10/31/2023 | Partial Approval | JAMES CHAVEZ |
| Rough-Elec/Plmb/HVAC | 10/31/2023 | Approved | JAMES CHAVEZ |
| Insulation | 11/6/2023 | Corrections Issued | JOHN KLARIN |
| Insulation | 11/9/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/27/2023 | Approved | JOHN KLARIN |
| Sewer | 1/12/2024 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/29/2024 | Partial Approval | BEN MOLSTAD |
| Final | 3/29/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/29/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 3/29/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 3/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 3/29/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 3/29/2024 | Approved | BEN MOLSTAD |
| Final | 4/3/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Pre-Inspection | 4/3/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 4/12/2024 | Approved | BEN MOLSTAD |
| Final | 4/12/2024 | OK to Issue CofO | BEN MOLSTAD |
| HVAC-Final | 4/12/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 4/12/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 4/12/2024 | Approved | BEN MOLSTAD |