2452 N JUPITER DR 90046
Certificate Information: 2452 N JUPITER DR 90046
- Application / Permit
- 22014-10000-06177
- Plan Check / Job No.
- B22LA25799
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel of Single Family Dwelling w/ attached garage, scope of work to include: (E) first floor partial remodel and rear addition; new roof at garage and entry; partial basement remodel and rear addition; renovation back yard and pool area.
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | EDWIN ESPIN |
| Corrections Issued | 1/10/2023 | EDWIN ESPIN |
| Quality Review Completed | 1/12/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/15/2023 | EDWIN ESPIN |
| Building Plans Picked Up | 2/16/2023 | APPLICANT |
| Applicant returned to address corrections | 3/17/2023 | EDWIN ESPIN |
| Plan Check Approved | 4/28/2023 | EDWIN ESPIN |
| Issued | 12/12/2023 | APPLICANT |
| CofO in Progress | 9/23/2025 | ROY SPAULDING |
| Permit Finaled | 10/2/2025 | DEROLD HAUFF |
| CofO Issued | 10/2/2025 | DEROLD HAUFF |
| Permit Finaled | 10/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/1/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 2/1/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 2/1/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 2/1/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 2/1/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | CINDY QI |
| Hydrant and Access approval | Cleared | 2/24/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 4/6/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/24/2023 | CINDY QI |
| Grading Pre-Inspection | Cleared | 4/28/2023 | EDWIN ESPIN |
Contact Information
| Architect | Griffin,, Margaret P; Lic. No.: C26524 | 1357 SUNSET AVENUE SANTA MONICA, CA 90405 |
| Contractor | Raub Doug Design & Development Inc; Lic. No.: 723625-B | 14066 ROBLAR ROAD SHERMAN OAKS, CA 91423 |
| Engineer | Berger,, Phillip Martin; Lic. No.: C13128 | 601 ARCADIA PL APT 203 NATIONAL CITY, CA 91950 |
| Engineer | Schmahl,, Lawrence Joseph; Lic. No.: L5748 | 11209 HOWARD STREET WHITTIER, CA 90606 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Hoek,, Johan; Lic. No.: EG2544 | 10369 SILVERSTON AVE TUJUNGA, CA 91042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/1/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/2/2024 | Conditional Approval | ROY SPAULDING |
| Deputy Other (see comments) | 4/5/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/8/2024 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 4/8/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/9/2024 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/7/2024 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/16/2024 | Corrections Issued | BRIAN SULLIVAN |
| Underground Mechanical | 5/16/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/21/2024 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/21/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 5/21/2024 | No Access for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/22/2024 | Conditional Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/23/2024 | Corrections Issued | RAUL BARAJAS |
| Underground Mechanical | 5/23/2024 | Partial Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/24/2024 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/31/2024 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 5/31/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 6/3/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/3/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 6/4/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/10/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/11/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/12/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/14/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/20/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/12/2024 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | RAUL BARAJAS |
| Deck | 8/21/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 9/30/2024 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/2/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 10/2/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/8/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/9/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 10/9/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/15/2024 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/15/2024 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/31/2024 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/31/2024 | Approved | BRIAN SULLIVAN |
| Wood Frame | 10/31/2024 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 11/15/2024 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 11/15/2024 | Partial Approval | NICHOLAS LOPEZ |
| Reinforced Concrete Frame | 12/18/2024 | Partial Approval | ROY SPAULDING |
| Structural Steel Frame | 12/18/2024 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Final | 3/6/2025 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 3/6/2025 | Approved | ROY SPAULDING |
| PLUMBING-Final | 3/6/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 4/22/2025 | Approved | ROY SPAULDING |
| Final | 4/22/2025 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 4/22/2025 | Approved | ROY SPAULDING |
| Green Building Final | 4/22/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 4/22/2025 | Approved | ROY SPAULDING |
| Final | 9/22/2025 | OK to Issue CofO | ROY SPAULDING |