12956 W WALSH AVE 90066

Certificate Information: 12956 W WALSH AVE 90066

Application / Permit
22014-10000-06173
Plan Check / Job No.
B22LA25762
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Addition to (E) SFD W/ attached garage
Permit Issued
Issued on 5/1/2023
Issuing Office
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 CRYSTEL MAALOUF
Corrections Issued 1/17/2023 CRYSTEL MAALOUF
Quality Review Completed 1/26/2023 GARO TELMI
Applicant returned to address corrections 4/26/2023 CRYSTEL MAALOUF
Plan Check Approved 5/1/2023 CRYSTEL MAALOUF
Issued 5/1/2023 APPLICANT
CofO in Progress 6/1/2024 TEMISTOCLES CAAL
Permit Finaled 6/6/2024 DANIEL ORRANTE
CofO Issued 6/6/2024 DANIEL ORRANTE
Permit Finaled 6/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 1/30/2023 ALESSANDRO MERCURI
Eng Process Fee Ord 176,300 Cleared 1/31/2023 JENSON LEE
Roof/Waste drainage to street Cleared 1/31/2023 JENSON LEE
Sewer availability Cleared 1/31/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2023 No Access for Inspection JESUS RODRIGUEZ
METHANE-Barrier 5/25/2023 No Access for Inspection JESUS RODRIGUEZ
METHANE-Subgrade 5/25/2023 No Access for Inspection JESUS RODRIGUEZ
Pre-Inspection 5/31/2023 Partial Inspection HERBERT GIRON
Pre-Inspection 8/24/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 10/5/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/5/2023 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 10/12/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 10/12/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved TEMISTOCLES CAAL
PLUMBING-Rough 11/13/2023 Approved TEMISTOCLES CAAL
HVAC-Rough 11/15/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 11/16/2023 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/22/2023 Not Ready for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/6/2023 Not Ready for Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 12/6/2023 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/7/2023 Approved TEMISTOCLES CAAL
Green Building Rough 12/7/2023 Approved TEMISTOCLES CAAL
Insulation 12/8/2023 Approved TEMISTOCLES CAAL
Shower Pan 12/8/2023 Approved TEMISTOCLES CAAL
Drywall Nailing 12/12/2023 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 12/19/2023 Not Ready for Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 12/21/2023 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 2/2/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 2/2/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/28/2024 Corrections Issued TEMISTOCLES CAAL
Final 3/28/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 3/28/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 3/28/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 4/5/2024 Approved TEMISTOCLES CAAL
Final 4/5/2024 Corrections Issued TEMISTOCLES CAAL
Service/Power Release 4/5/2024 Approved TEMISTOCLES CAAL
Smoke Detectors 4/5/2024 Approved TEMISTOCLES CAAL
Final 5/31/2024 OK to Issue CofO TEMISTOCLES CAAL