3884 S ALSACE AVE 90008

Certificate Information: 3884 S ALSACE AVE 90008

Application / Permit
22014-10000-06166
Plan Check / Job No.
B22LA25756
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION TO (E) GARAGE TO CREATE 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 11/24/2023
Issuing Office
Current Status
CofO Issued on 1/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/27/2022 DANIEL YIP
Corrections Issued 12/27/2022 DANIEL YIP
Applicant returned to address corrections 1/22/2023 KHUONG TRUONG
Applicant returned to address corrections 2/13/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 3/9/2023 DANIEL YIP
Plan Check Approved 3/14/2023 DANIEL YIP
Issued 11/24/2023 APPLICANT
CofO in Progress 12/20/2024 LUIS CASTRO
Permit Finaled 1/16/2025 DEROLD HAUFF
Permit Finaled 1/16/2025 DEROLD HAUFF
CofO Issued 1/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/5/2023 AMAAN MALIK
Low Impact Development Cleared 1/18/2023 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 1/19/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 1/19/2023 AMAAN MALIK
Sewer availability Cleared 1/19/2023 JEANIE LAM
Miscellaneous Cleared 1/23/2023 EDMOND LEE
Grading Pre-Inspection Cleared 1/26/2023 KIRK LINKLATER
GPI Written Notices Cleared 2/13/2023 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/16/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 2/23/2024 Corrections Issued BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 2/27/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 2/27/2024 Partial Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 3/11/2024 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 3/22/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 3/22/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/29/2024 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 4/2/2024 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/4/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 4/4/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/9/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 5/9/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 5/17/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval ANTHONY EGSON
Green Building Rough 5/17/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 5/29/2024 Corrections Issued ANTHONY EGSON
Green Building Final 5/29/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 5/29/2024 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 5/29/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 5/29/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 6/13/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 6/13/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 6/13/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 6/13/2024 Approved ANTHONY EGSON
PLUMBING-Rough 6/13/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/21/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/21/2024 Approved ANTHONY EGSON
Green Building Rough 6/21/2024 Approved ANTHONY EGSON
Insulation 6/28/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/28/2024 Corrections Issued ANTHONY EGSON
Underground Mechanical 6/28/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 7/2/2024 Approved ANTHONY EGSON
Drywall Nailing 7/5/2024 Corrections Issued ANTHONY EGSON
Drywall Nailing 7/11/2024 Approved ANTHONY EGSON
Service/Power Release 8/26/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 8/29/2024 Corrections Issued ANTHONY EGSON
Green Building Final 9/3/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 9/12/2024 Approved ANTHONY EGSON
Gas Test 9/12/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 11/20/2024 Approved BARRY HACHE
Final 11/20/2024 Corrections Issued BARRY HACHE
Green Building Final 11/20/2024 Approved BARRY HACHE
HVAC-Final 11/20/2024 Approved BARRY HACHE
PLUMBING-Final 11/20/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Not Ready BARRY HACHE
Service/Power Release 11/20/2024 Not Ready for Inspection BARRY HACHE
Smoke Detectors 11/20/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 11/21/2024 Approved BRENDAN MORELLI
Final 11/27/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready BARRY HACHE
Smoke Detectors 11/27/2024 Corrections Issued BARRY HACHE
Final 12/9/2024 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Not Ready BARRY HACHE
Smoke Detectors 12/9/2024 Not Ready for Inspection BARRY HACHE
Final 12/16/2024 Corrections Issued LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved LUIS CASTRO
Smoke Detectors 12/16/2024 Approved LUIS CASTRO
Final 12/19/2024 OK to Issue CofO LUIS CASTRO