3908 N RODERICK ROAD 90065

Certificate Information: 3908 N RODERICK ROAD 90065

Application / Permit
22014-10000-06131
Plan Check / Job No.
B22LA25624
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION AND REMODEL OF (E) 2-STORY SFD WITH ATTACHED DECK AND ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
Issued on 6/24/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 VIVIAN LAO
Corrections Issued 2/2/2023 VIVIAN LAO
Quality Review Completed 2/7/2023 KEN GILL
Building Plans Picked Up 2/9/2023 APPLICANT
Applicant returned to address corrections 5/29/2024 VIVIAN LAO
Plan Check Approved 6/24/2024 VIVIAN LAO
Issued 6/24/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/11/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 2/11/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 2/11/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 2/11/2023 TREVOR QUAN
Sewer availability Cleared 2/11/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/16/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 4/25/2023 TREVOR QUAN
ZI Cleared 5/8/2024 DALIA MOKAYED
GPI Written Notices Cleared 6/24/2024 VIVIAN LAO
Grading Pre-Inspection Cleared 6/24/2024 VIVIAN LAO

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Demers,, Joe Alan; Lic. No.: C71535 894 SANTA MARIA CIRCLE      DUARTE, CA 91010
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 7/10/2024 Partial Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 7/19/2024 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 7/22/2024 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 7/22/2024 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 7/24/2024 Approved CRAIG VAUGHAN
Deputy Reinf. Concrete 7/25/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 8/15/2024 Partial Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 8/29/2024 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 6/10/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 6/10/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 7/30/2025 No Access for Inspection NICHOLAS LOPEZ
PLUMBING-Rough 7/30/2025 No Access for Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 8/1/2025 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 8/1/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 12/1/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 12/1/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 2/4/2026 Approved NICHOLAS LOPEZ
Service/Power Release 2/4/2026 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 3/10/2026 Approved NICHOLAS LOPEZ
Green Building Rough 3/10/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 3/10/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 3/10/2026 Approved NICHOLAS LOPEZ
MERV13>=Rough 3/10/2026 Approved NICHOLAS LOPEZ
Wood Frame 3/10/2026 Approved NICHOLAS LOPEZ