10325 S LA SALLE AVE 90047

Certificate Information: 10325 S LA SALLE AVE 90047

Application / Permit
22014-10000-06112
Plan Check / Job No.
B22LA25523
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16'-0" x 18'-10" IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
Permit Issued
Issued on 4/4/2023
Issuing Office
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2022 APPLICANT
Assigned to Plan Check Engineer 12/30/2022 ADAM HEGAZI
Corrections Issued 1/3/2023 ADAM HEGAZI
Plan Check Approved 3/18/2023 SARKIS HARABEDIAN
Issued 4/4/2023 APPLICANT
CofO in Progress 9/20/2024 JOSE MACIAS
Permit Finaled 9/25/2024 RUBEN SALAS
CofO Issued 9/25/2024 RUBEN SALAS
Permit Finaled 9/25/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/27/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 2/28/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2023 Approved ENRIQUE MIRELES
Wood Frame 4/25/2023 Approved ENRIQUE MIRELES
Drywall Nailing 5/8/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 5/8/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/22/2023 Corrections Issued ENRIQUE MIRELES
METHANE-Barrier 6/22/2023 Approved ENRIQUE MIRELES
METHANE-Final 6/22/2023 Approved ENRIQUE MIRELES
METHANE-Rough 6/22/2023 Approved ENRIQUE MIRELES
METHANE-Subgrade 6/22/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Not Ready ENRIQUE MIRELES
Footing/Foundation/Slab 7/17/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 7/20/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 9/6/2023 Approved ENRIQUE MIRELES
Service/Power Release 9/6/2023 Approved ENRIQUE MIRELES
Drywall Nailing 9/14/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/2/2023 Approved ENRIQUE MIRELES
Green Building Rough 10/2/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/13/2023 Approved ENRIQUE MIRELES
Insulation 11/16/2023 Approved ENRIQUE MIRELES
Drywall Nailing 11/20/2023 Approved ENRIQUE MIRELES
Insulation 11/20/2023 Approved ENRIQUE MIRELES
Shower Pan 11/20/2023 Approved ENRIQUE MIRELES
Drywall Nailing 11/27/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/29/2023 Approved ENRIQUE MIRELES
Final 2/20/2024 Corrections Issued JOSE MACIAS
Green Building Final 2/20/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 2/20/2024 Approved JOSE MACIAS
Final 4/16/2024 Corrections Issued JOSE MACIAS
Final 8/30/2024 OK to Issue CofO JOSE MACIAS