951-952 N VENANGO AVE 90029
Certificate Information: 951-952 N VENANGO AVE 90029
- Application / Permit
- 22014-10000-06107
- Plan Check / Job No.
- B22LA25513
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST FLOOR EXPANSION AND RENOVATION / INTERIOR REMODELING NEW FRONT COVERED PORCH EXISTING RESIDENCE: 2 BEDROOM AND 1 BATH PROPOSED RESIDENCE: 3 BEDROOM AND 2 BATH CONVERSION OF GARAGE TO ADU AND ATTACH IT TO (E) SFD THRU ADDITION
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Metro
- Current Status
- Issued on 6/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | JAD BASMA |
| Corrections Issued | 1/9/2023 | JAD BASMA |
| Quality Review Completed | 1/13/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/23/2023 | APPLICANT |
| Applicant returned to address corrections | 1/31/2023 | JAD BASMA |
| Applicant returned to address corrections | 4/4/2023 | JAD BASMA |
| Applicant returned to address corrections | 6/15/2023 | JAD BASMA |
| Plan Check Approved | 6/15/2023 | JAD BASMA |
| Issued | 6/27/2023 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/7/2023 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 2/7/2023 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2023 | AMAAN MALIK |
| Low Impact Development | Cleared | 5/22/2023 | LUIS LUVANO |
| GPI Written Notices | Cleared | 5/24/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 5/24/2023 | JAD BASMA |
| Address approval | Cleared | 5/27/2023 | KEVIN AVILA |
| Roof/Waste drainage to street | Cleared | 5/27/2023 | KEVIN AVILA |
| Sewer availability | Cleared | 6/5/2023 | JEANIE LAM |
Contact Information
| Contractor | Orvis James Construction; Lic. No.: 568875-B | 5621 FALLSTON ST LOS ANGELES, CA 90042 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/14/2023 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Partial Inspection | FREDDIE RIVERA |
| Pre-Inspection | 3/1/2024 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/12/2024 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/12/2024 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/11/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 8/19/2024 | Partial Approval | FREDDIE RIVERA |
| Sewer | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/27/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/27/2026 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 1/27/2026 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | DAVID WILLIAMS |
| Green Building Rough | 5/22/2026 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 5/22/2026 | Approved | DAVID WILLIAMS |
| Insulation | 6/5/2026 | No Result Entered | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/5/2026 | No Result Entered | FREDDIE RIVERA |