9424 S LA SALLE AVE 90047
Certificate Information: 9424 S LA SALLE AVE 90047
- Application / Permit
- 22014-10000-06076
- Plan Check / Job No.
- B22LA25348
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-STORY ADU ADDITION TO (E) 1-STORY DETACHED GARAGE.
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Metro
- Current Status
- Issued on 2/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | VIVIAN LAO |
| Corrections Issued | 1/27/2023 | VIVIAN LAO |
| Quality Review Completed | 2/3/2023 | KEN GILL |
| Building Plans Picked Up | 2/8/2023 | APPLICANT |
| Applicant returned to address corrections | 4/3/2023 | VIVIAN LAO |
| Plan Check Approved | 2/1/2024 | VIVIAN LAO |
| Issued | 2/1/2024 | APPLICANT |
Permit Application Clearance Information
| Construction within easement | Cleared | 1/31/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/15/2023 | MELINEH AGHAKHABIAN |
| Address approval | Cleared | 3/23/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/23/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/28/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Jim C; Lic. No.: C69393 | 1822 E ROUTE 66, SUITE A, PO BOX 328 GLENDORA, CA 91740 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 3/5/2024 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 3/5/2024 | Approved | JOSE MACIAS |
| Pre-Inspection | 3/5/2024 | Approved | JOSE MACIAS |
| Deputy Drilled-In Anchors | 3/27/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 3/29/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/25/2024 | Partial Approval | JOSE MACIAS |
| PLUMBING-Rough | 4/25/2024 | Partial Approval | JOSE MACIAS |
| Insulation | 4/26/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Wood Construction | 9/12/2024 | No Access for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 11/18/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 11/18/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Rough | 11/18/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 11/18/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/25/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 11/25/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 11/25/2024 | Approved | AMIR NAZARIAN |
| Rough-Elec/Plmb/HVAC | 11/25/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Wood Frame | 11/25/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/27/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 11/27/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 11/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Insulation | 12/9/2024 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 12/19/2024 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 12/30/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 12/30/2024 | Approved | AMIR NAZARIAN |
| Sewer | 1/13/2025 | No Access for Inspection | SABAS ALONSO |
| Sewer | 1/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/11/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 7/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 7/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 7/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 7/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/10/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 7/10/2026 | Corrections Issued | SALVADOR MARTINEZ |