6227 S CIMARRON ST 90047

Certificate Information: 6227 S CIMARRON ST 90047

Application / Permit
22014-10000-06054
Plan Check / Job No.
B22LA25247
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION AT REAR OF (E) SFD, ADD WALK-IN CLOSET AND FULL BATHROOM PER W.F.P.P.
Permit Issued
Issued on 2/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2022 APPLICANT
Assigned to Plan Check Engineer 12/19/2022 LAWRENCE QUIRANTE
Corrections Issued 12/20/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 1/6/2023 APPLICANT
Plan Check Approved 2/7/2023 MINA HABILI
Issued 2/13/2023 APPLICANT
CofO in Progress 11/22/2023 CRAIG DAVIS
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/30/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/31/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/20/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 3/24/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 3/30/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/30/2023 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 3/31/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/17/2023 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 4/26/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 5/1/2023 Partial Approval STUART CHAPMAN
Insulation 5/8/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/7/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 8/7/2023 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/16/2023 Approved ENRIQUE MIRELES
Insulation 8/25/2023 Approved ENRIQUE MIRELES
Drywall Nailing 9/13/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 9/13/2023 Approved JUSTIN HAWLEY
HVAC-Rough 9/13/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/13/2023 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 9/13/2023 Approved JUSTIN HAWLEY
Shower Pan 9/13/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/25/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 9/27/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/30/2023 Approved CRAIG DAVIS
Final 10/30/2023 Corrections Issued CRAIG DAVIS
Green Building Final 10/30/2023 Approved CRAIG DAVIS
Green Building Rough 10/30/2023 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 10/30/2023 Corrections Issued CRAIG DAVIS
Special/Order Compliance 11/2/2023 Not Ready for Inspection CRAIG DAVIS
Final 11/6/2023 Partial Approval CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 11/6/2023 SGSOV Approved CRAIG DAVIS
Smoke Detectors 11/6/2023 Approved CRAIG DAVIS
Final 11/21/2023 OK to Issue CofO CRAIG DAVIS