3211 S BEVERLY DR 90034
Certificate Information: 3211 S BEVERLY DR 90034
- Application / Permit
- 22014-10000-06051
- Plan Check / Job No.
- B22LA25232
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan convert 342 ft detached garage and add to it 132 ft into an ADU 474SQFT
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- CofO Issued on 10/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2022 | KHUONG TRUONG |
| Corrections Issued | 12/20/2022 | KHUONG TRUONG |
| Plan Check Approved | 5/10/2023 | KHUONG TRUONG |
| Issued | 5/10/2023 | APPLICANT |
| CofO in Progress | 10/20/2023 | CLAYTON GRAHAM |
| Permit Finaled | 10/28/2023 | DANIEL ORRANTE |
| CofO Issued | 10/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 12/31/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 1/4/2023 | KYLE WINSTON |
| Grading Pre-Inspection | Cleared | 1/30/2023 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | SAUL GARCIA |
| Sewer availability | Cleared | 1/31/2023 | SAUL GARCIA |
| Construction near power lines | Cleared | 5/7/2023 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Butel Construction Inc; Lic. No.: 852273-B | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/15/2023 | Approved | CLAYTON GRAHAM |
| Underground Mechanical | 5/15/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Drilled-In Anchors | 5/22/2023 | Conditional Approval | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Approved | CLAYTON GRAHAM |
| Grounding or Bonding | 5/25/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 6/27/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 6/29/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 6/29/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 7/5/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 7/10/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/10/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 7/12/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 7/18/2023 | No Access for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 7/19/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 7/19/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/19/2023 | Approved | CLAYTON GRAHAM |
| Special/Order Compliance | 7/19/2023 | Partial Approval | CLAYTON GRAHAM |
| Gas Test | 8/29/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 9/28/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 9/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/28/2023 | Approved | ARAM AVEDISIAN |
| Green Building Final | 9/28/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 9/28/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 9/28/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/28/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/12/2023 | Approved | CLAYTON GRAHAM |
| Final | 10/12/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 10/12/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 10/19/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| HVAC-Final | 10/19/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 10/19/2023 | Approved | CLAYTON GRAHAM |