3211 S BEVERLY DR 90034

Certificate Information: 3211 S BEVERLY DR 90034

Application / Permit
22014-10000-06051
Plan Check / Job No.
B22LA25232
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan convert 342 ft detached garage and add to it 132 ft into an ADU 474SQFT
Permit Issued
Issued on 5/10/2023
Issuing Office
Current Status
CofO Issued on 10/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2022 APPLICANT
Assigned to Plan Check Engineer 12/19/2022 KHUONG TRUONG
Corrections Issued 12/20/2022 KHUONG TRUONG
Plan Check Approved 5/10/2023 KHUONG TRUONG
Issued 5/10/2023 APPLICANT
CofO in Progress 10/20/2023 CLAYTON GRAHAM
Permit Finaled 10/28/2023 DANIEL ORRANTE
CofO Issued 10/28/2023 DANIEL ORRANTE
Permit Finaled 10/28/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/31/2022 SAUL GARCIA
Roof/Waste drainage to street Cleared 12/31/2022 SAUL GARCIA
Specific Plan Cleared 1/4/2023 KYLE WINSTON
Grading Pre-Inspection Cleared 1/30/2023 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 1/31/2023 SAUL GARCIA
Sewer availability Cleared 1/31/2023 SAUL GARCIA
Construction near power lines Cleared 5/7/2023 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Butel Construction Inc; Lic. No.: 852273-B       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/15/2023 Approved CLAYTON GRAHAM
Underground Mechanical 5/15/2023 Partial Approval CLAYTON GRAHAM
Deputy Drilled-In Anchors 5/22/2023 Conditional Approval CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 5/25/2023 Approved CLAYTON GRAHAM
Grounding or Bonding 5/25/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 6/27/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 6/27/2023 Approved CLAYTON GRAHAM
Green Building Rough 6/27/2023 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Rough 6/29/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 6/29/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval CLAYTON GRAHAM
Shower Pan 7/5/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 7/10/2023 Approved CLAYTON GRAHAM
Green Building Rough 7/10/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 7/10/2023 Approved CLAYTON GRAHAM
Insulation 7/12/2023 Approved CLAYTON GRAHAM
Drywall Nailing 7/18/2023 No Access for Inspection ASHLEY THOMPSON
Drywall Nailing 7/19/2023 Approved CLAYTON GRAHAM
HVAC-Rough 7/19/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 7/19/2023 Approved CLAYTON GRAHAM
Special/Order Compliance 7/19/2023 Partial Approval CLAYTON GRAHAM
Gas Test 8/29/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
Final 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Final 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Final 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 9/28/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 9/28/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 9/28/2023 Approved ARAM AVEDISIAN
Green Building Final 9/28/2023 Approved ARAM AVEDISIAN
HVAC-Final 9/28/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 9/28/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/28/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 10/12/2023 Approved CLAYTON GRAHAM
Final 10/12/2023 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Final 10/12/2023 Corrections Issued CLAYTON GRAHAM
Final 10/19/2023 OK to Issue CofO CLAYTON GRAHAM
HVAC-Final 10/19/2023 Approved CLAYTON GRAHAM
Service/Power Release 10/19/2023 Approved CLAYTON GRAHAM