4110 S EAST BLVD 90066

Certificate Information: 4110 S EAST BLVD 90066

Application / Permit
22014-10000-06042
Plan Check / Job No.
B22LA25197
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 20'-0" x 17'-5" AT THE REAR TO (E) SINGLE FAMILY DWELLING TO ADD ONE BEDROOM, BATHROOM AND NEW ATTACHED 15'-0" X 6'-3" REAR DECK 2'-2" IN HEIGHT - WORK DONE PER ENGINEERING.
Permit Issued
Issued on 1/23/2023
Issuing Office
Current Status
CofO Issued on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2022 APPLICANT
Assigned to Plan Check Engineer 12/19/2022 MIROOSH KHACHATOORIAN
Corrections Issued 12/20/2022 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/3/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/11/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/18/2023 DANIEL ABRAMYAN
Plan Check Approved 1/23/2023 DANIEL ABRAMYAN
Issued 1/23/2023 APPLICANT
CofO in Progress 6/14/2023 JESUS RODRIGUEZ
Permit Finaled 6/23/2023 KENNETH NAGLE
CofO Issued 6/23/2023 KENNETH NAGLE
Permit Finaled 6/23/2023 KENNETH NAGLE

Permit Application Clearance Information

ZA Case Cleared 1/5/2023 LOUIS ORTEGA
Roof/Waste drainage to street Cleared 1/6/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/9/2023 DINAH GARIN
Specific Plan Cleared 1/17/2023 EDUARDO HERMOSO
Sewer availability Cleared 1/23/2023 DINAH GARIN

Contact Information

Contractor M D M Custom Remodeling Inc; Lic. No.: 930166-B       ,
Contractor Mdm General Contractor Room Additions; Lic. No.: 930166-B       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: NA88007       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/6/2023 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/6/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 2/6/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 2/9/2023 Partial Approval JESUS RODRIGUEZ
Underground Mechanical 2/9/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 2/10/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 3/2/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 3/2/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 3/2/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/7/2023 Approved JESUS RODRIGUEZ
Green Building Rough 3/7/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/7/2023 Approved JESUS RODRIGUEZ
Shower Pan 3/7/2023 Approved JESUS RODRIGUEZ
Insulation 3/21/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/21/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 3/29/2023 Approved HERBERT GIRON
ELECTRICAL-Final 5/17/2023 Approved BOBBY KEY
Final 5/17/2023 Corrections Issued BOBBY KEY
Green Building Final 5/17/2023 Approved BOBBY KEY
HVAC-Final 5/17/2023 Approved BOBBY KEY
PLUMBING-Final 5/17/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 5/17/2023 Approved BOBBY KEY
Final 6/13/2023 OK to Issue CofO JESUS RODRIGUEZ