205 N TIGERTAIL ROAD 90049

Certificate Information: 205 N TIGERTAIL ROAD 90049

Application / Permit
22014-10000-06036
Plan Check / Job No.
B22LA25185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Demolishing existing 484 squarefeet attached covered patio. Ground floor addition at the rear of the structure: 401 squarefeet on the NW side and 377 squarefeet on the SE side. Second floor addition: 31 square feet. Interior remodeling.
Permit Issued
Issued on 4/20/2023
Issuing Office
Current Status
Issued on 4/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 NGHI SU
Corrections Issued 1/12/2023 NGHI SU
Quality Review Completed 1/25/2023 GARO TELMI
Applicant returned to address corrections 2/23/2023 NGHI SU
Plan Check Approved 4/20/2023 NGHI SU
Issued 4/20/2023 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 1/11/2023 NGHI SU
BHO/Hillside ordinance Cleared 2/1/2023 VLADIMIR ARUTYUNYAN
BHO/Hillside ordinance Cleared 2/1/2023 VLADIMIR ARUTYUNYAN
BHO/Hillside ordinance Cleared 2/1/2023 VLADIMIR ARUTYUNYAN
BHO/Hillside ordinance Cleared 2/1/2023 VLADIMIR ARUTYUNYAN
BHO/Hillside ordinance Cleared 2/1/2023 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 2/1/2023 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 2/2/2023 JENSON LEE
Hydrant and Access approval Cleared 3/18/2023 RUEL COLE
Low Impact Development Cleared 3/29/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 3/31/2023 DINAH GARIN
Grading Pre-Inspection Cleared 4/14/2023 NGHI SU

Contact Information

Contractor Probity Construction & Development; Lic. No.: 1021792-B       ,
Engineer Masud,, Fahad M; Lic. No.: C92662 2415 EATON COURT      ORANGE, CA 92867
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/24/2023 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 4/25/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/25/2023 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/1/2023 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 5/1/2023 Approved KEVIN SARGSYAN
Sewer 5/6/2024 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 9/27/2024 Partial Inspection ARAM AVEDISIAN
HVAC-Rough 9/27/2024 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 9/27/2024 Partial Inspection ARAM AVEDISIAN
HVAC-Rough 11/1/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 11/5/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 11/21/2024 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 12/2/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/24/2025 Approved REGINA MENDEZ
Gas Test 3/19/2025 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 3/19/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/1/2025 No Access for Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/4/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/15/2025 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 4/16/2025 Corrections Issued KEVIN SARGSYAN
Green Building Rough 4/16/2025 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/16/2025 Approved KEVIN SARGSYAN
Shower Pan 5/6/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/7/2025 Corrections Issued KEVIN SARGSYAN
Wood Frame 5/21/2025 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 5/22/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 5/22/2025 Not Ready for Inspection KEVIN SARGSYAN
Insulation 5/27/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 5/27/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 6/16/2025 Approved MEL KHACHATOURIAN