6245 W 78TH ST 90045

Certificate Information: 6245 W 78TH ST 90045

Application / Permit
22014-10000-06033
Plan Check / Job No.
B22LA25182
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: DEMO (E) PORTIONS OF SFD AND (E) ATTACHED CARPORT, AND ADD 1,025 SF SINGLE STORY to (E) SFD. INTERIOR AND EXTERIOR REMODEL TO (E) SFD.
Permit Issued
Issued on 6/29/2023
Issuing Office
Current Status
Issued on 6/29/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/14/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 SUNMIN LEE
Corrections Issued 1/18/2023 SUNMIN LEE
Quality Review Completed 1/18/2023 GARO TELMI
Applicant returned to address corrections 2/16/2023 SUNMIN LEE
Applicant returned to address corrections 3/21/2023 SUNMIN LEE
Applicant returned to address corrections 4/5/2023 SUNMIN LEE
Applicant returned to address corrections 4/18/2023 SUNMIN LEE
Applicant returned to address corrections 5/26/2023 SUNMIN LEE
Plan Check Approved 6/29/2023 SUNMIN LEE
Issued 6/29/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/3/2023 MICHAEL TEMPLE
Sewer availability Cleared 4/7/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/14/2023 DINAH GARIN
Low Impact Development Cleared 5/3/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/4/2023 JASON NG
Specific Plan Cleared 5/18/2023 JOSHUA JONES
GPI Written Notices Cleared 6/7/2023 SUNMIN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Landers,, Jesse Eugene; Lic. No.: C83060 1139 1/2 NW 52ND STREET      SEATTLE, WA 98665
Engineer Landers,, Jesse Eugene; Lic. No.: NA83060       ,
Engineer Rios,, Anthony; Lic. No.: L9343 14726 WEEPING WILLOW LN      FONTANA, CA 92337

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2023 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 7/14/2023 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 7/14/2023 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 8/25/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 10/18/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 11/30/2023 Approved BOBBY KEY
Sewer 11/30/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 1/10/2024 Approved BOBBY KEY
Special/Order Compliance 1/10/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 1/18/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/8/2024 Corrections Issued BOBBY KEY
HVAC-Rough 2/8/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 3/13/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 3/13/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 3/13/2024 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 3/13/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 3/26/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 4/10/2024 Corrections Issued BOBBY KEY
HVAC-Rough 4/10/2024 Approved BOBBY KEY
Interior/Exterior Lathing 4/10/2024 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 4/16/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 4/16/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 5/21/2024 Approved BOBBY KEY
Insulation 6/14/2024 Corrections Issued TEMISTOCLES CAAL
Drywall Nailing 7/22/2024 Approved RICHARD STEINBACH
Insulation 7/22/2024 Approved RICHARD STEINBACH
Interior/Exterior Lathing 10/22/2024 Approved TEMISTOCLES CAAL
Shower Pan 10/22/2024 Approved TEMISTOCLES CAAL
Gas Test 4/8/2025 Partial Inspection JESUS PINEDA
Pre-Inspection 4/8/2025 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 4/10/2025 Corrections Issued TEMISTOCLES CAAL
Gas Test 4/10/2025 Approved TEMISTOCLES CAAL
HVAC-Final 4/10/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 4/17/2025 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 5/1/2025 Approved JESUS PINEDA
HVAC-Final 5/1/2025 Not Ready for Inspection JESUS PINEDA
Final 5/8/2025 Corrections Issued JESUS PINEDA
HVAC-Final 5/8/2025 Approved JESUS PINEDA
PLUMBING-Final 5/8/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 5/8/2025 Approved JESUS PINEDA
PLUMBING-Final 6/2/2025 Approved JESUS PINEDA
Final 6/3/2025 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 6/27/2025 Approved DAVID FEILER