**EPLAN** Convert Existing detached Storage and portion of detached Garage into Accessory Dwelling Unit per engineer details (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 GEORGE ALVAREZ
Corrections Issued 1/12/2023 GEORGE ALVAREZ
Applicant returned to address corrections 1/30/2023 AUNG SOE
Plan Check Approved 2/15/2023 AUNG SOE
Issued 2/28/2023 APPLICANT
CofO in Progress 7/5/2024 JOSE MACIAS
Permit Finaled 7/24/2024 DEROLD HAUFF
CofO Issued 7/24/2024 DEROLD HAUFF
Permit Finaled 7/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2023 CELINA MORENO
Sewer availability Cleared 1/26/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/27/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/3/2023 Corrections Issued STUART CHAPMAN
Deputy Drilled-In Anchors 4/4/2023 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 5/3/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/5/2023 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/5/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/5/2023 Not Ready for Inspection ENRIQUE MIRELES
Sewer 5/5/2023 Corrections Issued ENRIQUE MIRELES
Wood Frame 5/5/2023 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 5/11/2023 Approved ENRIQUE MIRELES
Drywall Nailing 5/18/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Approved ENRIQUE MIRELES
Gas Test 5/18/2023 Approved ENRIQUE MIRELES
Sewer 5/18/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/25/2023 Approved ENRIQUE MIRELES
Shower Pan 5/25/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/1/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 6/7/2023 Approved ENRIQUE MIRELES
Deputy Wood Construction 7/10/2023 Approved ENRIQUE MIRELES
Final 12/28/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/28/2023 Approved ENRIQUE MIRELES
Pre-Inspection 6/10/2024 Corrections Issued JOSE MACIAS
Service/Power Release 6/10/2024 Not Ready for Inspection JOSE MACIAS
Final 6/14/2024 Corrections Issued JOSE MACIAS
Final 7/1/2024 OK to Issue CofO JOSE MACIAS