5760 W 74TH ST 90045

Certificate Information: 5760 W 74TH ST 90045

Application / Permit
22014-10000-05986
Plan Check / Job No.
B22LA24849
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (18'-6"x12'-7"), 217 SQFT 2ND STORY ADDITION ABOVE THE EXISTING ATTACHED GARAGE TO THE EXISTING SINGLE FAMILY DWELLING.
Permit Issued
Issued on 11/25/2023
Issuing Office
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 PETER MOSESIAN
Corrections Issued 1/19/2023 PETER MOSESIAN
Quality Review Completed 1/19/2023 OMID HEDAYAT
Applicant returned to address corrections 2/27/2023 PETER MOSESIAN
Plan Check Approved 5/3/2023 PETER MOSESIAN
Issued 11/25/2023 APPLICANT
CofO in Progress 4/8/2025 TEMISTOCLES CAAL
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 2/6/2023 ALESSANDRO MERCURI
Roof/Waste drainage to street Cleared 2/13/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 3/2/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Partial Inspection JESUS PINEDA
Footing/Foundation/Slab 7/12/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 9/17/2024 Approved BOBBY KEY
Special/Order Compliance 9/17/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/18/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 10/18/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 10/18/2024 Approved TEMISTOCLES CAAL
MERV13>=Rough 10/18/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 10/18/2024 Not Ready for Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/11/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 12/11/2024 Corrections Issued HERBERT GIRON
MERV13>=Rough 12/11/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 12/11/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 1/10/2025 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 1/10/2025 Approved TEMISTOCLES CAAL
MERV13>=Rough 1/10/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 1/10/2025 Corrections Issued TEMISTOCLES CAAL
Insulation 1/15/2025 Approved EVAN COOPER
Drywall Nailing 1/22/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 3/21/2025 Approved JESUS PINEDA
Drywall Nailing 3/21/2025 Approved JESUS PINEDA
Final 3/21/2025 Corrections Issued JESUS PINEDA
MERV13>=Final 3/21/2025 Approved JESUS PINEDA
PLUMBING-Rough 3/21/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 3/21/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 4/7/2025 Approved TEMISTOCLES CAAL
Final 4/7/2025 OK to Issue CofO TEMISTOCLES CAAL
HVAC-Final 4/7/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 4/7/2025 Approved TEMISTOCLES CAAL
Smoke Detectors 4/7/2025 Approved TEMISTOCLES CAAL