22940 W AUSTIN ST 91364

Certificate Information: 22940 W AUSTIN ST 91364

Application / Permit
22014-10000-05946
Plan Check / Job No.
B22LA24620
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO SFD PER ENGINEER CALCS - REMODEL EXISITING DWELLING - EXISITING 4 BEDROOMS AND 3 BATHROOMS TO BE NEW 6 BEDROOMS AND 5.5 BATHROOMS - MEP PERMIT REQUIRED. NEW AIR/HEAT, NEW WATER HEATER, NEW ROOF SHINGLES, COOLROOF, SRI-16
Permit Issued
Issued on 3/29/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 ARSALAN SHABESTARI
Corrections Issued 12/22/2022 ARSALAN SHABESTARI
Quality Review Completed 1/6/2023 KEN GILL
Building Plans Picked Up 1/9/2023 APPLICANT
Plan Check Approved 3/28/2023 ARSALAN SHABESTARI
Issued 3/29/2023 APPLICANT
CofO in Progress 9/25/2023 PETER FOLLING
Permit Finaled 2/26/2024 JOHN JANSON
CofO Issued 2/26/2024 JOHN JANSON
Permit Finaled 2/26/2024 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/26/2023 RYAN KIM
BHO/Hillside ordinance Cleared 1/26/2023 RYAN KIM
BHO/Hillside ordinance Cleared 1/26/2023 RYAN KIM
BHO/Hillside ordinance Cleared 1/26/2023 RYAN KIM
BHO/Hillside ordinance Cleared 1/26/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 1/31/2023 RYAN KIM
Sewer availability Cleared 1/31/2023 RYAN KIM
Hydrant and Access approval Cleared 3/10/2023 GILBERT URREA
Low Impact Development Cleared 3/15/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 3/15/2023 RYAN KIM
GPI Written Notices Cleared 3/28/2023 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 3/28/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/6/2023 Partial Approval PETER FOLLING
Footing/Foundation/Slab 4/12/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Corrections Issued PETER FOLLING
ELECTRICAL-Rough 6/13/2023 Approved PETER FOLLING
HVAC-Rough 6/13/2023 Corrections Issued PETER FOLLING
PLUMBING-Rough 6/13/2023 Approved PETER FOLLING
Wood Frame 6/13/2023 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 6/16/2023 Corrections Issued PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Partial Approval PETER FOLLING
HVAC-Rough 6/16/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 6/23/2023 Partial Approval PETER FOLLING
Green Building Rough 6/23/2023 Approved PETER FOLLING
Insulation 6/23/2023 Approved PETER FOLLING
Interior/Exterior Lathing 6/23/2023 Partial Approval PETER FOLLING
Verify Sprinkler Sign Off 6/23/2023 Approved PETER FOLLING
Drywall Nailing 6/28/2023 Approved PETER FOLLING
Shower Pan 6/28/2023 Approved PETER FOLLING
Interior/Exterior Lathing 6/30/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/7/2023 Approved PETER FOLLING
Final 9/7/2023 Corrections Issued PETER FOLLING
Green Building Final 9/7/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Not Ready PETER FOLLING
Smoke Detectors 9/7/2023 Approved PETER FOLLING
Final 9/22/2023 OK to Issue CofO PETER FOLLING
SGSOV-Seismic Gas S/O Valve 9/22/2023 SGSOV Approved PETER FOLLING