2670 1/2 E ROSEVIEW AVE 90065
Certificate Information: 2670 1/2 E ROSEVIEW AVE 90065
- Application / Permit
- 22014-10000-05945
- Plan Check / Job No.
- B22LA24616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT ADDITION ON TOP OF EXISTING GARAGE PER LAMC 12.22A.33(c) AND (d)
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 1/11/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/23/2023 | APPLICANT |
| Plan Check Approved | 9/25/2023 | DANIEL YIP |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 9/19/2024 | OSVALDO PARAMO |
| Permit Finaled | 11/14/2024 | DEROLD HAUFF |
| CofO Issued | 11/14/2024 | DEROLD HAUFF |
| Permit Finaled | 11/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 3/23/2023 | KIRK LINKLATER |
| ZI | Cleared | 4/19/2023 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 6/14/2023 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/15/2023 | JEANIE LAM |
| Sewer availability | Cleared | 7/28/2023 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 8/1/2023 | ISMAEL HERNANDEZ |
| ZI | Cleared | 8/4/2023 | ANDREA MAGANA-WITHERS |
| GPI Written Notices | Cleared | 9/1/2023 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/29/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Pre-Inspection | 9/29/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 11/2/2023 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/8/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 11/8/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/30/2023 | Corrections Issued | OSVALDO PARAMO |
| Shower Pan | 11/30/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/1/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/1/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/1/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 12/1/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/4/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 12/4/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 12/7/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/7/2023 | Approved | OSVALDO PARAMO |
| Insulation | 12/12/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 12/15/2023 | Approved | OSVALDO PARAMO |
| Final | 7/1/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/1/2024 | Approved | OSVALDO PARAMO |
| Gas Test | 7/1/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 7/1/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/1/2024 | Approved | OSVALDO PARAMO |
| Final | 9/10/2024 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 9/10/2024 | Approved | OSVALDO PARAMO |