2670 1/2 E ROSEVIEW AVE 90065

Certificate Information: 2670 1/2 E ROSEVIEW AVE 90065

Application / Permit
22014-10000-05945
Plan Check / Job No.
B22LA24616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT ADDITION ON TOP OF EXISTING GARAGE PER LAMC 12.22A.33(c) AND (d)
Permit Issued
Issued on 9/26/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 MARCELA FRANQUEZ
Corrections Issued 1/11/2023 MARCELA FRANQUEZ
Quality Review Completed 1/19/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/23/2023 APPLICANT
Plan Check Approved 9/25/2023 DANIEL YIP
Issued 9/26/2023 APPLICANT
CofO in Progress 9/19/2024 OSVALDO PARAMO
Permit Finaled 11/14/2024 DEROLD HAUFF
CofO Issued 11/14/2024 DEROLD HAUFF
Permit Finaled 11/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/8/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/9/2023 JEANIE LAM
Grading Pre-Inspection Cleared 3/23/2023 KIRK LINKLATER
ZI Cleared 4/19/2023 RUBEN VASQUEZ
Low Impact Development Cleared 6/14/2023 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/15/2023 JEANIE LAM
Sewer availability Cleared 7/28/2023 JEANIE LAM
Tenant Habitability Plan Cleared 8/1/2023 ISMAEL HERNANDEZ
ZI Cleared 8/4/2023 ANDREA MAGANA-WITHERS
GPI Written Notices Cleared 9/1/2023 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2023 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/29/2023 Partial Approval ALIZAH MAYAGOITIA
Pre-Inspection 9/29/2023 Partial Inspection ALIZAH MAYAGOITIA
Deputy Wood Construction 11/2/2023 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 11/8/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Corrections Issued OSVALDO PARAMO
Green Building Rough 11/8/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 11/30/2023 Corrections Issued OSVALDO PARAMO
Shower Pan 11/30/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/1/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/1/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 12/1/2023 Approved HAMIK HARTOUNIAN
Shower Pan 12/1/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/4/2023 Approved OSVALDO PARAMO
HVAC-Rough 12/4/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/7/2023 Approved OSVALDO PARAMO
Green Building Rough 12/7/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/7/2023 Approved OSVALDO PARAMO
Insulation 12/12/2023 Approved OSVALDO PARAMO
Drywall Nailing 12/15/2023 Approved OSVALDO PARAMO
Final 7/1/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 7/1/2024 Approved OSVALDO PARAMO
Gas Test 7/1/2024 Approved OSVALDO PARAMO
Green Building Final 7/1/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 7/1/2024 Approved OSVALDO PARAMO
Final 9/10/2024 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 9/10/2024 Approved OSVALDO PARAMO