1530 N ORANGE GROVE AVE 90046

Certificate Information: 1530 N ORANGE GROVE AVE 90046

Application / Permit
22014-10000-05926
Plan Check / Job No.
B22LA24482
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Remodel (E) SFD and additions to first and second floor.
Permit Issued
Issued on 2/24/2023
Issuing Office
Current Status
Issued on 2/24/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/5/2022 APPLICANT
Assigned to Plan Check Engineer 12/13/2022 HELEN NGUYEN
Corrections Issued 12/14/2022 HELEN NGUYEN
Quality Review Completed 12/28/2022 MICHAEL PEREZ
Applicant returned to address corrections 1/5/2023 HELEN NGUYEN
Applicant returned to address corrections 1/13/2023 HELEN NGUYEN
Applicant returned to address corrections 1/19/2023 HELEN NGUYEN
Applicant returned to address corrections 1/20/2023 HELEN NGUYEN
Plan Check Approved 1/31/2023 HELEN NGUYEN
Issued 2/24/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/23/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/23/2022 AMAAN MALIK
Sewer availability Cleared 12/23/2022 AMAAN MALIK
HPOZ Cleared 1/13/2023 AMANDA KAINER

Contact Information

Contractor Mota Builders Inc; Lic. No.: 1070384-B       ,
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/18/2023 Partial Inspection RAUL BARAJAS
Special/Order Compliance 5/19/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 7/12/2023 Partial Approval STUART CHAPMAN
Pre-Inspection 7/12/2023 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 8/22/2023 Approved RAUL BARAJAS
Structural Steel Frame 8/22/2023 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 1/11/2024 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval STUART CHAPMAN
Wood Frame 1/16/2024 Partial Approval STUART CHAPMAN
Masonry Wall/Backfill 3/5/2024 Not Ready for Inspection RAUL BARAJAS
Shower Pan 3/5/2024 Corrections Issued RAUL BARAJAS
Underground Mechanical 3/7/2024 Approved RAUL BARAJAS
HVAC-Rough 3/13/2024 Corrections Issued BRIAN SULLIVAN
Shower Pan 3/13/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Final 3/22/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 3/22/2024 Approved RAUL BARAJAS
HVAC-Rough 3/22/2024 Partial Inspection RAUL BARAJAS
Shower Pan 3/22/2024 Approved RAUL BARAJAS
PLUMBING-Rough 3/28/2024 Conditional Approval BRIAN SULLIVAN
Interior/Exterior Lathing 4/3/2024 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 4/15/2024 Corrections Issued RAUL BARAJAS
Wood Frame 4/15/2024 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 5/8/2024 Conditional Approval BRIAN SULLIVAN
Insulation 5/8/2024 Approved BRIAN SULLIVAN
Drywall Nailing 5/22/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/17/2025 Approved ROY SPAULDING
Final 7/17/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Approved ROY SPAULDING
Smoke Detectors 7/17/2025 Approved ROY SPAULDING
Final 7/24/2025 Conditional Approval ROY SPAULDING