500 WORLD WAY 90045
Certificate Information: 500 WORLD WAY 90045
- Application / Permit
- 22014-10000-05919
- Plan Check / Job No.
- B22LA24450
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX** RENOVATION OF GATE 51 A/B HOLD ROOM AND CONSTRUCTION OF A NEW SECURE PEDESTRIAN ACCESS BRIDGE TO T4. MODIFICATION OF SPACE TO A BAGGAGE STORAGE OFFICE AND OFFICE MANAGER AT LEVEL 1. APRON REPAIR AT GATE 51A.
- Permit Issued
- Issued on 2/13/2024
- Issuing Office
- Current Status
- Issued on 2/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/23/2023 | DEAN RYAN REYES |
| Quality Review Completed | 1/26/2023 | LIPING TENG |
| Applicant returned to address corrections | 8/15/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 8/30/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 8/31/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/1/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/31/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/6/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/8/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/13/2024 | FARSHAD ALIMOHAMADI |
| Issued | 2/13/2024 | APPLICANT |
Permit Application Clearance Information
| Project Permit | Cleared | 4/25/2023 | DEAN RYAN REYES |
| City owned building/parcel | Cleared | 5/3/2023 | DEAN RYAN REYES |
| Hydrant and Access approval | Cleared | 6/30/2023 | JOHN CONNEALLY |
| Airport buildings | Cleared | 11/16/2023 | ANDREW KO |
| Fire Marshal Fire Life Safety | Cleared | 11/16/2023 | ANDREW KO |
| Sewer availability | Cleared | 11/20/2023 | AHMED AMARRAGY |
| Green Code | Cleared | 12/5/2023 | AARON COSTA |
| Low Impact Development | Cleared | 1/15/2024 | ORVAL HERNANDEZ-MARCI |
| DAS Clearance | Cleared | 1/22/2024 | Lily Teng |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 1/24/2024 | AHMED AMARRAGY |
| Building over 36-ft | Cleared | 2/9/2024 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 2/9/2024 | CALOSHA APPROVED |
Contact Information
| Architect | Gerber,, Jeffrey P; Lic. No.: C27945 | 14 ESTANCIA PLACE THE WOODLANDS, TX 77309 |
| Contractor | Hensel Phelps Construction Co; Lic. No.: 1020262-B | , |
| Engineer | Bouquet,, Thomas Campbell; Lic. No.: S4007 | 155 N LAKE AVE SUITE 600 PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| T-Bar Ceiling | 1/16/2025 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 1/17/2025 | Partial Approval | ALAN NOVAK |
| Final | 2/13/2025 | No Access for Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 2/13/2025 | Approved | ALAN NOVAK |
| Green Building Final | 2/13/2025 | Approved | ALAN NOVAK |
| Green Building Rough | 2/13/2025 | Approved | ALAN NOVAK |
| METHANE-Barrier | 2/13/2025 | Approved | ALAN NOVAK |
| METHANE-Final | 2/13/2025 | Approved | ALAN NOVAK |
| METHANE-Rough | 2/13/2025 | Approved | ALAN NOVAK |
| METHANE-Subgrade | 2/13/2025 | Approved | ALAN NOVAK |
| Reinforced Concrete Frame | 2/13/2025 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 2/13/2025 | Approved | ALAN NOVAK |
| Structural Steel Frame | 2/13/2025 | Approved | ALAN NOVAK |
| Final | 2/19/2025 | Not Ready for Inspection | ALAN NOVAK |
| Pre-Inspection | 2/21/2025 | Approved | ALAN NOVAK |