838 S RIMPAU BLVD 90005
Certificate Information: 838 S RIMPAU BLVD 90005
- Application / Permit
- 22014-10000-05917
- Plan Check / Job No.
- B22LA24435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *eplan* ADD TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/19/2023 | SELLA BENYAMIN |
| Quality Review Completed | 1/26/2023 | STEVEN KIM |
| Applicant returned to address corrections | 3/9/2023 | SELLA BENYAMIN |
| Plan Check Approved | 3/10/2023 | SELLA BENYAMIN |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 4/10/2024 | JEFFREY MEAD |
| Permit Finaled | 4/12/2024 | DEROLD HAUFF |
| CofO Issued | 4/12/2024 | DEROLD HAUFF |
| Permit Finaled | 4/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 2/25/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 2/27/2023 | TREVOR QUAN |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 4/28/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 4/28/2023 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 4/28/2023 | Partial Inspection | LILIANA PORTILLO |
| Underground Mechanical | 5/9/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/18/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 6/1/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Other (see comments) | 6/1/2023 | Partial Approval | JEFFREY MEAD |
| METHANE-Rough | 6/1/2023 | Approved | JEFFREY MEAD |
| Wood Frame | 6/1/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 8/10/2023 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/15/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 8/15/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 8/17/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/17/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 8/17/2023 | Approved | JEFFREY MEAD |
| Insulation | 8/22/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/22/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 9/11/2023 | Approved | JEFFREY MEAD |
| Shower Pan | 9/11/2023 | Approved | JEFFREY MEAD |
| Sewer | 10/6/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/11/2023 | Approved | JEFFREY MEAD |
| Service/Power Release | 11/9/2023 | Corrections Issued | JEFFREY MEAD |
| Service/Power Release | 11/13/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 11/30/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 12/27/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/28/2024 | Approved | JEFFREY MEAD |
| Final | 2/28/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/28/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 2/28/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 2/28/2024 | Approved | JEFFREY MEAD |
| Final | 4/9/2024 | OK to Issue CofO | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Approved | JEFFREY MEAD |