3768 S HARVARD BLVD 1-3 90018
Certificate Information: 3768 S HARVARD BLVD 1-3 90018
- Application / Permit
- 22014-10000-05911
- Plan Check / Job No.
- B22LA24421
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2nd floor addition to (E) SFD to create 2nd Unit and convert portion of existing dwelling to ADU.
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2023 | HERNAN ARREOLA |
| Corrections Issued | 1/28/2023 | HERNAN ARREOLA |
| Quality Review Completed | 1/31/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 4/19/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/15/2023 | HERNAN ARREOLA |
| Plan Check Approved | 8/31/2023 | HERNAN ARREOLA |
| Issued | 9/28/2023 | APPLICANT |
| CofO in Progress | 8/14/2025 | SABAS ALONSO |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
| CofO Issued | 8/15/2025 | DEROLD HAUFF |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 4/6/2023 | JENNIFER SU |
| Address approval | Cleared | 4/22/2023 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 4/27/2023 | CHRISTOPHER ROCHA |
| Low Impact Development (LID) | Cleared | 8/21/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/23/2023 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2023 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 2/26/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/10/2024 | Approved | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 6/10/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/21/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 6/21/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 7/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 7/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 9/23/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 9/30/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 9/30/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/8/2024 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 10/8/2024 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 10/10/2024 | Approved | SABAS ALONSO |
| Sewer | 10/10/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 10/16/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/18/2024 | Approved | SABAS ALONSO |
| Insulation | 10/29/2024 | Corrections Issued | SABAS ALONSO |
| Insulation | 11/7/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/18/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/27/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 12/3/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/5/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 5/5/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 5/5/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 5/9/2025 | Approved | SABAS ALONSO |
| Final | 5/20/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 5/20/2025 | Approved | SABAS ALONSO |
| Green Building Final | 5/20/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 5/20/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/20/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 5/20/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/3/2025 | No Access for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 7/3/2025 | No Access for Inspection | LUIS CASTRO |
| Final | 8/4/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 8/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 8/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 8/11/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 8/11/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/11/2025 | Approved | SABAS ALONSO |
| Final | 8/13/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 8/13/2025 | Approved | SABAS ALONSO |