4561 W MONROE ST 90029

Certificate Information: 4561 W MONROE ST 90029

Application / Permit
22014-10000-05895
Plan Check / Job No.
B22LA24383
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU AND ADDITION PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 3/10/2023
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/12/2022 JOE VO
Corrections Issued 12/13/2022 VIVIAN LAO
Applicant returned to address corrections 2/23/2023 HERNAN ARREOLA
Applicant returned to address corrections 3/6/2023 MICHAEL LOPEZ
Plan Check Approved 3/8/2023 JOE VO
Issued 3/10/2023 APPLICANT
CofO in Progress 8/31/2023 FREDDIE RIVERA
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/21/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 12/21/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/3/2023 STEVE MELGAR
Sewer availability Cleared 1/3/2023 STEVE MELGAR
Specific Plan Cleared 2/13/2023 DANALYNN DOMINGUEZ

Contact Information

Contractor Dreamworks Builders; Lic. No.: 1052079-B       ,
Contractor Liam & Adam Associates Inc; Lic. No.: 1052079-B       ,
Engineer Southerland,, Richard Charles; Lic. No.: C88965 16526 BLACKHAWK ST      GRANADA HILLS, CA 91344

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/30/2023 Partial Inspection STUART CHAPMAN
ELECTRICAL-Rough 4/21/2023 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/21/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 4/21/2023 Partial Approval FREDDIE RIVERA
Sewer 4/21/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/1/2023 Partial Approval FREDDIE RIVERA
Gas Test 5/1/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 5/1/2023 Partial Approval FREDDIE RIVERA
Sewer 5/1/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 5/11/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/23/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/23/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval FREDDIE RIVERA
Gas Test 5/23/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 5/23/2023 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/23/2023 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 5/23/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Ready FREDDIE RIVERA
Sewer 5/23/2023 Partial Inspection FREDDIE RIVERA
Wood Frame 5/23/2023 Partial Inspection FREDDIE RIVERA
Insulation 5/24/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 6/6/2023 Approved FREDDIE RIVERA
Green Building Rough 6/6/2023 Approved FREDDIE RIVERA
HVAC-Rough 6/6/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/6/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/8/2023 Approved ALIZAH MAYAGOITIA
Insulation 6/8/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/15/2023 Approved FREDDIE RIVERA
Final 8/15/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/15/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 8/15/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 8/17/2023 Approved FREDDIE RIVERA
Final 8/21/2023 Conditional Approval FREDDIE RIVERA
Green Building Final 8/21/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/21/2023 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 8/21/2023 Approved FREDDIE RIVERA