1536 S 5TH AVE 90019

Certificate Information: 1536 S 5TH AVE 90019

Application / Permit
22014-10000-05893
Plan Check / Job No.
B22LA24380
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED (22'-0" x 22'-5") ADDITION TO THE (E) DETACHED GARAGE FOR A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 11/16/2023
Issuing Office
Current Status
CofO Issued on 1/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2022 APPLICANT
Assigned to Plan Check Engineer 12/9/2022 ROSENDO MEDINA
Corrections Issued 12/13/2022 ROSENDO MEDINA
Plan Check Approved 4/12/2023 SARKIS HARABEDIAN
Issued 11/16/2023 APPLICANT
CofO in Progress 1/16/2026 WILLIAM SIERRA
Permit Finaled 1/17/2026 DEROLD HAUFF
CofO Issued 1/17/2026 DEROLD HAUFF
Permit Finaled 1/17/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/19/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/1/2023 TREVOR QUAN
Sewer availability Cleared 2/1/2023 TREVOR QUAN
Community Plan Implem. Overlay Cleared 4/7/2023 KYLE WINSTON
Low Impact Development Cleared 4/10/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 4/11/2023 DAVID VO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2023 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/11/2023 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Barrier 12/11/2023 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 12/11/2023 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/13/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 2/26/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Approved ARTHUR NEGRETE
Green Building Rough 2/26/2024 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Rough 2/26/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 3/20/2024 Approved ARTHUR NEGRETE
HVAC-Rough 3/20/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/20/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Approved WILLIAM SIERRA
Insulation 10/8/2024 Corrections Issued WILLIAM SIERRA
HVAC-Rough 11/1/2024 Approved WILLIAM SIERRA
Insulation 11/1/2024 Corrections Issued WILLIAM SIERRA
Insulation 11/5/2024 Approved WILLIAM SIERRA
Drywall Nailing 11/7/2024 Approved WILLIAM SIERRA
Shower Pan 11/20/2024 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 4/21/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 4/21/2025 Corrections Issued BRENDAN MORELLI
Final 4/21/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 4/21/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 4/21/2025 Approved BRENDAN MORELLI
HVAC-Final 4/21/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 4/21/2025 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV No Gas BRENDAN MORELLI
Smoke Detectors 4/21/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 12/2/2025 Approved WILLIAM SIERRA
Final 12/2/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 12/2/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 12/2/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 12/2/2025 Approved WILLIAM SIERRA
Smoke Detectors 12/2/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 1/16/2026 Approved WILLIAM SIERRA
Final 1/16/2026 OK to Issue CofO WILLIAM SIERRA
Green Building Final 1/16/2026 Approved WILLIAM SIERRA
HVAC-Final 1/16/2026 Approved WILLIAM SIERRA
PLUMBING-Final 1/16/2026 Approved WILLIAM SIERRA
Service/Power Release 1/16/2026 Not Required WILLIAM SIERRA