21914 S HARVARD BLVD 90501

Certificate Information: 21914 S HARVARD BLVD 90501

Application / Permit
22014-10000-05890
Plan Check / Job No.
B22LA24356
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD TO CONNECT TO (E) GARAGE, PORTION OF (E) GARAGE CONVERTED TO ATTACHED ADU WITH AN ADDITION PER ATTACHED ADU ORDINANCE
Permit Issued
Issued on 6/2/2023
Issuing Office
Current Status
CofO Issued on 4/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 CARLOS MONTES
Corrections Issued 1/19/2023 CARLOS MONTES
Quality Review Completed 1/19/2023 GARO TELMI
Applicant returned to address corrections 5/4/2023 CARLOS MONTES
Plan Check Approved 5/18/2023 CARLOS MONTES
Issued 6/2/2023 APPLICANT
CofO in Progress 4/4/2024 EUGENE CASSIDY
Permit Finaled 4/4/2024 ANSON MAGLASANG
CofO Issued 4/4/2024 ANSON MAGLASANG
Permit Finaled 4/4/2024 ANSON MAGLASANG

Permit Application Clearance Information

SB8 RUD Cleared 2/14/2023 JESSICA WANG
Low Impact Development Cleared 3/16/2023 LUIS LUVANO
Address approval Cleared 3/22/2023 KHAING AYE
Roof/Waste drainage to street Cleared 3/22/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 3/28/2023 KHAING AYE
Sewer availability Cleared 3/29/2023 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/23/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 7/3/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/3/2023 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 7/10/2023 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 7/14/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/18/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 7/21/2023 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/21/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/13/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 9/13/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/2/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 10/2/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/2/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/23/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 11/2/2023 Approved EUGENE CASSIDY
HVAC-Rough 11/2/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/14/2023 Approved EUGENE CASSIDY
Green Building Rough 11/14/2023 Approved EUGENE CASSIDY
Insulation 11/14/2023 Approved EUGENE CASSIDY
Drywall Nailing 11/27/2023 Approved EUGENE CASSIDY
Final 2/21/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/21/2024 Approved EUGENE CASSIDY
Green Building Final 2/21/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/21/2024 Approved EUGENE CASSIDY
Final 3/27/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 3/27/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 4/3/2024 Approved EUGENE CASSIDY
Final 4/3/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 4/3/2024 Approved EUGENE CASSIDY
HVAC-Final 4/3/2024 Approved EUGENE CASSIDY
PLUMBING-Final 4/3/2024 Approved EUGENE CASSIDY
Service/Power Release 4/4/2024 Approved EUGENE CASSIDY