429 1/2 S MATHEWS ST 90033

Certificate Information: 429 1/2 S MATHEWS ST 90033

Application / Permit
22014-10000-05881
Plan Check / Job No.
B22LA24311
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE AND (N) 5'5" X 24' IRREGULARLY SHAPED ADDITION (236 SF) TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 11/14/2023
Issuing Office
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2022 APPLICANT
Assigned to Plan Check Engineer 12/9/2022 GEORGE ALVAREZ
Corrections Issued 12/12/2022 GEORGE ALVAREZ
Applicant returned to address corrections 3/17/2023 MADISON ODELL
Plan Check Approved 5/7/2023 MADISON ODELL
Issued 11/14/2023 APPLICANT
CofO in Progress 7/17/2025 FREDDIE RIVERA
Permit Finaled 7/18/2025 DEROLD HAUFF
CofO Issued 7/18/2025 DEROLD HAUFF
Permit Finaled 7/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/16/2022 KIRK LINKLATER
Address approval Cleared 12/21/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 12/21/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/30/2022 TREVOR QUAN
Sewer availability Cleared 12/30/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 2/9/2024 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 2/9/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 2/9/2024 Approved FREDDIE RIVERA
Pre-Inspection 2/9/2024 Approved FREDDIE RIVERA
Footing/Foundation/Slab 2/23/2024 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 2/23/2024 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 2/23/2024 Partial Inspection FREDDIE RIVERA
Sewer 4/18/2024 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/13/2024 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 6/13/2024 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 6/13/2024 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 6/13/2024 Corrections Issued FREDDIE RIVERA
Deputy Methane Barrier 11/4/2024 Conditional Approval JOHN QUINTANILLA
METHANE-Subgrade 11/5/2024 Approved FREDDIE RIVERA
Deputy Methane Barrier 11/7/2024 Conditional Approval JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 11/13/2024 Approved FREDDIE RIVERA
METHANE-Barrier 11/13/2024 Approved FREDDIE RIVERA
Underground Mechanical 11/13/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval JUSTIN HAWLEY
Special/Order Compliance 1/14/2025 Corrections Issued JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Approved FREDDIE RIVERA
ELECTRICAL-Rough 2/12/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 2/12/2025 Approved FREDDIE RIVERA
Shower Pan 2/12/2025 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 3/10/2025 Approved FREDDIE RIVERA
Green Building Rough 3/10/2025 Approved FREDDIE RIVERA
HVAC-Rough 3/10/2025 Approved FREDDIE RIVERA
METHANE-Rough 3/10/2025 Approved FREDDIE RIVERA
Wood Frame 3/10/2025 Partial Inspection FREDDIE RIVERA
Drywall Nailing 3/12/2025 Partial Inspection FREDDIE RIVERA
Insulation 3/12/2025 Corrections Issued FREDDIE RIVERA
Insulation 3/17/2025 Approved FREDDIE RIVERA
Drywall Nailing 4/2/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 4/2/2025 Approved JOSH MEISTER
Shower Pan 4/2/2025 Approved JOSH MEISTER
ELECTRICAL-Final 6/23/2025 Partial Inspection FREDDIE RIVERA
Final 6/23/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 6/23/2025 Approved FREDDIE RIVERA
Gas Test 6/23/2025 Approved FREDDIE RIVERA
HVAC-Final 6/23/2025 Approved FREDDIE RIVERA
PLUMBING-Final 6/23/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 6/23/2025 Corrections Issued FREDDIE RIVERA
Smoke Detectors 6/23/2025 Approved FREDDIE RIVERA
Final 7/9/2025 Corrections Issued FREDDIE RIVERA
Service/Power Release 7/9/2025 Approved FREDDIE RIVERA
Final 7/17/2025 OK to Issue CofO FREDDIE RIVERA