521 N MARTEL AVE 90036
Certificate Information: 521 N MARTEL AVE 90036
- Application / Permit
- 22014-10000-05879
- Plan Check / Job No.
- B22LA24306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) ONE-STORY HOUSE.
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | JOE VO |
| Corrections Issued | 12/11/2022 | JOE VO |
| Quality Review Completed | 12/23/2022 | MICHAEL PEREZ |
| Building Plans Picked Up | 12/28/2022 | APPLICANT |
| Plan Check Approved | 6/2/2023 | JOE VO |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 12/31/2025 | JOSH MEISTER |
| Permit Finaled | 12/31/2025 | DEROLD HAUFF |
| Permit Finaled | 12/31/2025 | DEROLD HAUFF |
| CofO Issued | 12/31/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/27/2023 | KURT CORRAL |
| Specific Plan | Cleared | 5/11/2023 | SEGAL ISMAEL |
| Permit | Cleared | 5/18/2023 | CELINA MORENO |
| Sewer availability | Cleared | 5/18/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2023 | CELINA MORENO |
| Low Impact Development | Cleared | 5/24/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/30/2023 | WALLIE JONG |
Contact Information
| Contractor | Psg Hardware & Supply; Lic. No.: 1079377-B | 10418 GLADE AVENUE CHATSWORTH, CA 91311 |
| Engineer | Luisoni,, Antonio Stefano; Lic. No.: S1781 | 12757 DEON PLACE GRANADA HILLS, CA 91344 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 8/25/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 8/25/2023 | Corrections Issued | LILIANA PORTILLO |
| METHANE-Rough | 9/5/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/5/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Subgrade | 11/3/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/29/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/7/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Methane Barrier | 12/8/2023 | Conditional Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 12/8/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 3/7/2024 | Conditional Approval | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Partial Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 4/24/2024 | Partial Inspection | AMIR NAZARIAN |
| METHANE-Barrier | 4/24/2024 | Partial Inspection | AMIR NAZARIAN |
| METHANE-Final | 4/24/2024 | Partial Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 5/6/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 5/7/2024 | Corrections Issued | AMIR NAZARIAN |
| Deputy Wood Construction | 5/7/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 5/7/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 8/28/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 8/28/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 8/28/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Final | 8/28/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 8/28/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 9/10/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/10/2024 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/10/2024 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 9/10/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/10/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Service/Power Release | 9/10/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 9/26/2024 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/3/2024 | Corrections Issued | JOSE MACIAS |
| METHANE-Barrier | 10/3/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/3/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 10/4/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 11/22/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 11/22/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/22/2024 | Approved | JOSE MACIAS |
| Insulation | 12/18/2024 | Approved | ALEX COLIN |
| Shower Pan | 12/18/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 1/7/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/7/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 5/13/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 5/13/2025 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 5/22/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 5/30/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 8/25/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 8/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 8/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/15/2025 | SGSOV Not Ready | JOSE MACIAS |
| Final | 9/19/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 9/19/2025 | Approved | JOSE MACIAS |
| Green Building Final | 9/19/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 9/19/2025 | Approved | JOSE MACIAS |
| Smoke Detectors | 9/19/2025 | Approved | JOSE MACIAS |
| Final | 10/15/2025 | Not Ready for Inspection | JOSH MEISTER |
| Final | 11/20/2025 | Not Ready for Inspection | JOSH MEISTER |
| Final | 11/24/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/5/2025 | Corrections Issued | JOSH MEISTER |
| Final | 12/5/2025 | Corrections Issued | JOSH MEISTER |
| HVAC-Final | 12/5/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 12/5/2025 | Approved | JOSH MEISTER |
| Service/Power Release | 12/5/2025 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 12/9/2025 | Approved | JOSH MEISTER |
| Gas Test | 12/9/2025 | Approved | JOSH MEISTER |
| HVAC-Final | 12/9/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 12/9/2025 | Approved | JOSH MEISTER |
| Final | 12/23/2025 | Conditional Approval | ENRIQUE MIRELES |
| Final | 12/29/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 12/30/2025 | OK to Issue CofO | JOSH MEISTER |