3317 W ATWATER AVE 90039

Certificate Information: 3317 W ATWATER AVE 90039

Application / Permit
22014-10000-05877
Plan Check / Job No.
B22LA24304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
34'-9" X 18'-8" ADDITION, REMODEL AND COMPLEE RE-ROOF OF EXISTING SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER ***NFPA-13D FIRE SPRINKLER REQUIRED THROUGHOUT
Permit Issued
Issued on 4/26/2023
Issuing Office
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2022 APPLICANT
Assigned to Plan Check Engineer 12/7/2022 DANIEL ABRAMYAN
Corrections Issued 12/8/2022 DANIEL ABRAMYAN
Plan Check Approved 4/25/2023 DANIEL ABRAMYAN
Issued 4/26/2023 APPLICANT
CofO in Progress 4/26/2024 CHARLES BOGHOSKHAN
CofO Issued 4/29/2024 DEROLD HAUFF
Permit Finaled 4/29/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 12/24/2022 STEVEN WECHSLER
Sewer availability Cleared 12/30/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/3/2023 AMAAN MALIK
Low Impact Development Cleared 1/11/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 3/9/2023 AMAAN MALIK
Miscellaneous Cleared 4/25/2023 EDMOND LEE

Contact Information

Contractor A To Z Construction Inc; Lic. No.: 988824-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/15/2023 Conditional Approval CHARLES BOGHOSKHAN
Footing/Foundation/Slab 5/17/2023 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved JOSEPH MCGARRY
Pre-Inspection 5/22/2023 Partial Inspection SCOTT FINNILA
Special/Order Compliance 5/22/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/30/2023 Partial Approval SCOTT FINNILA
Insulation 5/30/2023 Partial Approval SCOTT FINNILA
PLUMBING-Rough 5/30/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/4/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 8/4/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/1/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 9/1/2023 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 9/5/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/18/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 9/18/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/18/2023 Partial Approval BRIAN SULLIVAN
Insulation 10/2/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/2/2023 Approved HAMIK HARTOUNIAN
Shower Pan 10/2/2023 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 10/10/2023 Approved HAMIK HARTOUNIAN
Gas Test 10/10/2023 Approved HAMIK HARTOUNIAN
Final 3/28/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/28/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 3/28/2024 Approved HAMIK HARTOUNIAN
Final 4/9/2024 Corrections Issued HAMIK HARTOUNIAN
Final 4/25/2024 OK to Issue CofO CHARLES BOGHOSKHAN