2245 S MALCOLM AVE 90064
Certificate Information: 2245 S MALCOLM AVE 90064
- Application / Permit
- 22014-10000-05875
- Plan Check / Job No.
- B22LA24295
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1ST FLOOR ADDITION (395 SQFT) AND 2ND FLOOR ADDITION (567 SQFT),TO THE EXISTING 1-STORY SINGLE FAMILY DWELLING W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | PETER MOSESIAN |
| Corrections Issued | 2/18/2023 | PETER MOSESIAN |
| Quality Review Completed | 2/24/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/17/2023 | PETER MOSESIAN |
| Plan Check Approved | 7/14/2023 | PETER MOSESIAN |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 5/21/2026 | ARAM AVEDISIAN |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | DENNIS BRAGIN |
| Sewer availability | Cleared | 2/27/2023 | DENNIS BRAGIN |
| Specific Plan | Cleared | 2/27/2023 | WESTON PRINGLE |
| Specific Plan | Cleared | 3/7/2023 | ANACANY HURTADO |
| ZI | Cleared | 3/7/2023 | ANACANY HURTADO |
| Stormwater Pollution Mitigatn | Cleared | 4/14/2023 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/19/2023 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/15/2023 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 11/21/2023 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/4/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 12/4/2023 | Corrections Issued | JESUS PINEDA |
| Wood Frame | 12/7/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 4/15/2024 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 5/31/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 5/31/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 5/31/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 6/20/2024 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 6/20/2024 | Approved | SEAN HAUPT |
| Wood Frame | 6/26/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/9/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 7/9/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/9/2024 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 7/9/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | KIRK SANDERS |
| Insulation | 7/16/2024 | No Access for Inspection | KIRK SANDERS |
| Insulation | 7/18/2024 | Approved | JESUS PINEDA |
| Shower Pan | 7/18/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/6/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/17/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 12/3/2024 | Approved | REGINA MENDEZ |
| Special/Order Compliance | 2/12/2025 | Approved | EVAN COOPER |
| Service/Power Release | 4/4/2025 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/4/2025 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Final | 6/10/2025 | Partial Inspection | ARAM AVEDISIAN |
| Special/Order Compliance | 8/8/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 3/17/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 3/17/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/17/2026 | Approved | ARAM AVEDISIAN |
| METHANE-Final | 3/17/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 3/17/2026 | Approved | ARAM AVEDISIAN |
| Final | 5/15/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 5/21/2026 | OK to Issue CofO | ARAM AVEDISIAN |