816-818 W 130TH ST 90247
Certificate Information: 816-818 W 130TH ST 90247
- Application / Permit
- 22014-10000-05873
- Plan Check / Job No.
- B22LA24288
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) Rear Bedroom and (N) Addition to ADU per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 5/3/2023
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2022 | JOHNPAUL ISIP |
| Corrections Issued | 12/12/2022 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 4/12/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/21/2023 | DAVID CASTILLO |
| Plan Check Approved | 4/26/2023 | JOHNPAUL ISIP |
| Issued | 5/3/2023 | APPLICANT |
| CofO in Progress | 1/12/2024 | JAMES CHAVEZ |
| Permit Finaled | 1/12/2024 | ANSON MAGLASANG |
| CofO Issued | 1/12/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/12/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2023 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/22/2023 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/22/2023 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: C43117 | 9234 STAMPS AVE DOWNEY, CA 90240 |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: NA43117 | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/26/2023 | Corrections Issued | JAMES CHAVEZ |
| METHANE-Barrier | 5/26/2023 | Approved | JAMES CHAVEZ |
| METHANE-Subgrade | 5/26/2023 | Approved | JAMES CHAVEZ |
| Pre-Inspection | 6/1/2023 | Partial Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/13/2023 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 7/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 7/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 8/3/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 8/3/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/3/2023 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 8/3/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/15/2023 | Approved | JAMES CHAVEZ |
| Insulation | 8/18/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 8/29/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 8/29/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/29/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/12/2023 | Approved | JOHN KLARIN |
| Final | 12/12/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 12/12/2023 | Approved | JOHN KLARIN |
| Gas Test | 12/12/2023 | Approved | JOHN KLARIN |
| Green Building Final | 12/12/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 12/12/2023 | Approved | JOHN KLARIN |
| MERV13>=Final | 12/12/2023 | Approved | JOHN KLARIN |
| MERV13>=Rough | 12/12/2023 | Approved | JOHN KLARIN |
| METHANE-Final | 12/12/2023 | Approved | JOHN KLARIN |
| METHANE-Rough | 12/12/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/12/2023 | Approved | JOHN KLARIN |
| Final | 1/9/2024 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 1/9/2024 | Approved | JAMES CHAVEZ |