8822 S LILIENTHAL AVE 90045
Certificate Information: 8822 S LILIENTHAL AVE 90045
- Application / Permit
- 22014-10000-05871
- Plan Check / Job No.
- B22LA24257
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion of a permitted detached garage and a permitted detached workshop to an Accessory Dwelling Unit (ADU) PER LAMC 12.22 A.33 (c) AND (d)
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Current Status
- Issued on 4/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | DANIEL SANJUAN |
| Corrections Issued | 12/9/2022 | DANIEL SANJUAN |
| Plan Check Approved | 4/14/2023 | ARSALAN SHABESTARI |
| Issued | 4/20/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 1/11/2023 | DANIEL CORONADO |
| Construction near power lines | Cleared | 3/21/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2024 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 2/11/2025 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 2/11/2025 | Corrections Issued | ANDREW BEELI |
| Pre-Inspection | 2/11/2025 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 2/25/2025 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 3/6/2025 | Approved | ANDREW BEELI |
| Pre-Inspection | 3/6/2025 | Approved | ANDREW BEELI |
| Pre-Inspection | 4/3/2025 | Corrections Issued | ANDREW BEELI |
| Pre-Inspection | 4/10/2025 | Approved | ANDREW BEELI |
| ELECTRICAL-Rough | 4/14/2025 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 4/14/2025 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Final | 4/22/2025 | Corrections Issued | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Approved | ANDREW BEELI |
| Insulation | 4/22/2025 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 4/22/2025 | Approved | ANDREW BEELI |
| PLUMBING-Final | 4/22/2025 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 5/9/2025 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 5/9/2025 | Not Ready for Inspection | ANDREW BEELI |
| Underground Mechanical | 5/9/2025 | Approved | ANDREW BEELI |
| Drywall Nailing | 5/22/2025 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 5/22/2025 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 5/22/2025 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 5/27/2025 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 5/27/2025 | Not Ready for Inspection | ANDREW BEELI |
| Gas Test | 5/27/2025 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 5/29/2025 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 5/29/2025 | Not Ready for Inspection | ANDREW BEELI |
| Gas Test | 5/29/2025 | Approved | ANDREW BEELI |
| HVAC-Rough | 5/29/2025 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 5/29/2025 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 6/18/2025 | Approved | ANDREW BEELI |
| ELECTRICAL-Rough | 6/18/2025 | Approved | ANDREW BEELI |
| Drywall Nailing | 7/25/2025 | Approved | ANDREW BEELI |
| HVAC-Rough | 7/25/2025 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 7/25/2025 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 9/4/2025 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 9/4/2025 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Final | 9/4/2025 | Not Ready for Inspection | ANDREW BEELI |
| Service/Power Release | 9/4/2025 | Approved | ANDREW BEELI |
| Pre-Inspection | 10/17/2025 | Approved | ANDREW BEELI |
| Service/Power Release | 10/17/2025 | Approved | ANDREW BEELI |
| Pre-Inspection | 10/29/2025 | Approved | ANDREW BEELI |
| Service/Power Release | 10/29/2025 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 11/12/2025 | Approved | ANDREW BEELI |
| Green Building Final | 11/12/2025 | Approved | ANDREW BEELI |
| Green Building Rough | 11/12/2025 | Approved | ANDREW BEELI |
| Pre-Inspection | 11/12/2025 | Approved | ANDREW BEELI |
| Final | 11/26/2025 | Partial Approval | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | ANDREW BEELI |
| Smoke Detectors | 11/26/2025 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 1/21/2026 | Approved | ANDREW BEELI |
| HVAC-Final | 1/21/2026 | Approved | ANDREW BEELI |
| HVAC-Rough | 1/21/2026 | Approved | ANDREW BEELI |
| MERV13>=Rough | 1/21/2026 | Approved | ANDREW BEELI |
| METHANE-Final | 1/21/2026 | Approved | ANDREW BEELI |
| METHANE-Rough | 1/21/2026 | Approved | ANDREW BEELI |
| PLUMBING-Final | 1/21/2026 | Approved | ANDREW BEELI |