12976 W SHORT AVE 90066
Certificate Information: 12976 W SHORT AVE 90066
- Application / Permit
- 22014-10000-05869
- Plan Check / Job No.
- B22LA24236
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 2/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2022 | WEIJIAN HUANG |
| Corrections Issued | 12/8/2022 | WEIJIAN HUANG |
| Building Plans Picked Up | 12/9/2022 | APPLICANT |
| Plan Check Approved | 2/17/2023 | FERNANDO FLORES |
| Issued | 2/22/2023 | APPLICANT |
| CofO in Progress | 6/3/2025 | RUBEN RIVAS |
| Permit Finaled | 6/6/2025 | RICHARD STEINBACH |
| CofO Issued | 6/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/5/2023 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 1/23/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2023 | DINAH GARIN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Celtic Design And Construction; Lic. No.: 778960-B | 2633 LINCOLN BLVD #304 SANTA MONICA, CA 90405 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 2/23/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Barrier | 2/23/2023 | Approved | HERBERT GIRON |
| METHANE-Subgrade | 2/23/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 3/14/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 5/17/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 5/17/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 5/17/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/17/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Rough | 5/17/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/23/2023 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 5/23/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 5/24/2023 | Approved | HERBERT GIRON |
| Shower Pan | 5/24/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/25/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 6/8/2023 | Approved | HERBERT GIRON |
| Insulation | 6/8/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 10/24/2023 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 10/24/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 10/24/2023 | Approved | TEMISTOCLES CAAL |
| Final | 11/15/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/15/2023 | Corrections Issued | HERBERT GIRON |
| Final | 12/4/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Smoke Detectors | 12/4/2023 | Approved | TEMISTOCLES CAAL |
| Final | 6/2/2025 | OK to Issue CofO | RUBEN RIVAS |