1773 1/2 S BEDFORD ST 90035

Certificate Information: 1773 1/2 S BEDFORD ST 90035

Application / Permit
22014-10000-05867
Plan Check / Job No.
B22LA24219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ADU AND NEW ADDITION PER LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 9/18/2023
Issuing Office
Metro
Current Status
CofO in Progress on 8/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 MARCELA FRANQUEZ
Corrections Issued 12/13/2022 MARCELA FRANQUEZ
Quality Review Completed 12/21/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/10/2023 APPLICANT
Applicant returned to address corrections 1/30/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 5/8/2023 MARCELA FRANQUEZ
Plan Check Approved 9/13/2023 MARCELA FRANQUEZ
Issued 9/18/2023 APPLICANT
CofO in Progress 8/5/2025 PETER RUBIO

Permit Application Clearance Information

Address approval Cleared 3/20/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/20/2023 JEANIE LAM
Sewer availability Cleared 3/20/2023 JEANIE LAM
Low Impact Development Cleared 8/30/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/30/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/28/2023 Corrections Issued ROBERT NILES
Pre-Inspection 11/28/2023 Not Ready for Inspection ROBERT NILES
Sewer 11/28/2023 Not Ready for Inspection ROBERT NILES
Footing/Foundation/Slab 12/5/2023 Corrections Issued ROBERT NILES
METHANE-Barrier 12/5/2023 Approved ROBERT NILES
METHANE-Subgrade 12/5/2023 Approved ROBERT NILES
Excavation/Setback/Form/Re-Bar 12/6/2023 Corrections Issued ROBERT NILES
PLUMBING-Rough 12/6/2023 Partial Approval ROBERT NILES
Pre-Inspection 12/6/2023 Not Ready for Inspection ROBERT NILES
Excavation/Setback/Form/Re-Bar 12/13/2023 Corrections Issued ROBERT NILES
Excavation/Setback/Form/Re-Bar 12/14/2023 Corrections Issued ROBERT NILES
Excavation/Setback/Form/Re-Bar 12/18/2023 Approved ROBERT NILES
BUILDING-Rough-Frame 4/10/2024 Partial Approval EMIL OPFFER
ELECTRICAL-Rough 4/10/2024 Not Ready for Inspection EMIL OPFFER
Green Building Rough 4/10/2024 Not Ready for Inspection EMIL OPFFER
HVAC-Rough 4/10/2024 Conditional Approval EMIL OPFFER
METHANE-Rough 4/10/2024 Not Ready for Inspection EMIL OPFFER
PLUMBING-Rough 4/10/2024 Conditional Approval EMIL OPFFER
Wood Frame 4/10/2024 Conditional Approval EMIL OPFFER
Interior/Exterior Lathing 5/28/2024 Approved ROBERT NILES
Insulation 7/29/2024 Corrections Issued ROBERT NILES
Drywall Nailing 8/26/2024 Approved ROBERT NILES
Green Building Rough 8/26/2024 Approved ROBERT NILES
ELECTRICAL-Final 3/24/2025 Not Ready for Inspection PETER RUBIO
Gas Test 3/24/2025 Approved PETER RUBIO
PLUMBING-Final 3/24/2025 Approved PETER RUBIO
BUILDING-Rough-Frame 5/21/2025 Not Ready for Inspection PETER RUBIO
Final 5/21/2025 Not Ready for Inspection PETER RUBIO
Footing/Foundation/Slab 5/21/2025 Approved PETER RUBIO
Green Building Final 5/21/2025 Not Ready for Inspection PETER RUBIO
METHANE-Final 5/21/2025 Approved PETER RUBIO
METHANE-Rough 5/21/2025 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Ready PETER RUBIO
Smoke Detectors 5/21/2025 Not Ready for Inspection PETER RUBIO
BUILDING-Rough-Frame 7/22/2025 Approved PETER RUBIO
Final 7/22/2025 Not Ready for Inspection PETER RUBIO
Green Building Final 7/22/2025 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved PETER RUBIO
Smoke Detectors 7/22/2025 Approved PETER RUBIO
Final 8/1/2025 OK to Issue CofO PETER RUBIO