12415 W KLING ST 91604
Certificate Information: 12415 W KLING ST 91604
- Application / Permit
- 22014-10000-05861
- Plan Check / Job No.
- B22LA24159
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODELING AND TWO STORY ADDTION WITH ATTACEHED GARAGE
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | JOE VO |
| Corrections Issued | 12/10/2022 | JOE VO |
| Quality Review Completed | 12/13/2022 | GARO TELMI |
| Plan Check Approved | 3/16/2023 | JOE VO |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 3/28/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/15/2024 | RUBEN SALAS |
| Permit Finaled | 4/15/2024 | RUBEN SALAS |
| CofO Issued | 4/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Permit | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/30/2023 | KURT CORRAL |
| Sewer availability | Cleared | 2/2/2023 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 2/8/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/13/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/24/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/24/2023 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 6/13/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 6/14/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/2/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/2/2023 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 8/2/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 8/2/2023 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 8/2/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 8/3/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/9/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/11/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/18/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 8/18/2023 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 8/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/18/2023 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 8/18/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/25/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/25/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/25/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/5/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 9/18/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 10/2/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/2/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 2/20/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 2/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Final | 2/20/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 2/26/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 2/26/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 2/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 3/28/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 3/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 3/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/28/2024 | Approved | CHRISTOPHE COCHRAN |