3711 N LOMITAS DR 90032
Certificate Information: 3711 N LOMITAS DR 90032
- Application / Permit
- 22014-10000-05816
- Plan Check / Job No.
- B22LA23900
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY ADDITION AND PATIO COVER W/ DECK TO AT REAR OF (E) 1-STORY SFD. SEE COMMENTS.
- Permit Issued
- Issued on 7/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2022 | FERNANDO FLORES |
| Corrections Issued | 12/3/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 12/7/2022 | APPLICANT |
| Applicant returned to address corrections | 12/30/2022 | MINA HABILI |
| Applicant returned to address corrections | 5/24/2023 | MINA HABILI |
| Applicant returned to address corrections | 7/14/2023 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/19/2023 | MINA HABILI |
| Plan Check Approved | 7/19/2023 | STANLEY RAAP |
| Issued | 7/19/2023 | APPLICANT |
| CofO in Progress | 10/3/2024 | LILIANA PORTILLO |
| CofO Issued | 10/15/2024 | RUBEN SALAS |
| Permit Finaled | 10/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/24/2023 | WALLIE JONG |
| "D" conditions | Cleared | 6/20/2023 | DALIA MOKAYED |
| "Q" conditions | Cleared | 6/20/2023 | DALIA MOKAYED |
| ZI | Cleared | 6/20/2023 | DALIA MOKAYED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/7/2023 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 9/13/2023 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 9/19/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 10/3/2023 | Corrections Issued | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 10/3/2023 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 10/3/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 11/9/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/14/2024 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 2/14/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/14/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/5/2024 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/5/2024 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 3/28/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/28/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/4/2024 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/4/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 4/4/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/24/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/24/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 4/24/2024 | Approved | LILIANA PORTILLO |
| Insulation | 4/30/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/17/2024 | Approved | LILIANA PORTILLO |
| Final | 9/3/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 9/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 9/3/2024 | Approved | LILIANA PORTILLO |
| Final | 9/6/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 9/6/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/2/2024 | Approved | LILIANA PORTILLO |
| Final | 10/2/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 10/2/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/2/2024 | Approved | LILIANA PORTILLO |