1183-1185 S MCCLELLAN DR 90049
Certificate Information: 1183-1185 S MCCLELLAN DR 90049
- Application / Permit
- 22014-10000-05807
- Plan Check / Job No.
- B22LA23857
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF (E) SFD TO ATTACHED ADU WITH AN ADDTION PER ATTACHED ADU ORDINANCE & GROUND FLOOR AND SECOND FLOOR ADDITION TO (E) SFD (2-STORY)
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- CofO Issued on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | CARLOS MONTES |
| Corrections Issued | 12/24/2022 | CARLOS MONTES |
| Quality Review Completed | 12/27/2022 | GARO TELMI |
| Plan Check Approved | 7/7/2023 | CARLOS MONTES |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | KIRK SANDERS |
| Permit Finaled | 7/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/15/2025 | RICHARD STEINBACH |
| CofO Issued | 7/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2023 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 1/5/2023 | DANIEL SCHNEIDEREIT |
| Trees in Parkway | Cleared | 2/1/2023 | ADALBERTO VERA |
| Address approval | Cleared | 6/13/2023 | ANTHONY MAINEZ |
| Permit | Cleared | 6/13/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/13/2023 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 6/19/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/20/2023 | JASON NG |
| Specific Plan | Cleared | 6/29/2023 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hsiao,, Stephanie; Lic. No.: NA75937 | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2024 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 6/10/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/24/2024 | Partial Approval | KIRK SANDERS |
| Sewer | 6/24/2024 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 6/24/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/28/2024 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 6/28/2024 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 6/28/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 7/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| Special/Order Compliance | 7/22/2024 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 7/29/2024 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 7/29/2024 | Approved | KIRK SANDERS |
| Special/Order Compliance | 7/29/2024 | Partial Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/30/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 9/30/2024 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 9/30/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 9/30/2024 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 9/30/2024 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 10/1/2024 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 10/10/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | KIRK SANDERS |
| Deputy Steel/Welding | 10/15/2024 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 10/15/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 10/15/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 10/15/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/7/2024 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 11/7/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 11/7/2024 | Approved | KIRK SANDERS |
| Insulation | 11/7/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 11/7/2024 | Partial Approval | KIRK SANDERS |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | KENNETH NAGLE |
| Insulation | 11/13/2024 | Approved | KENNETH NAGLE |
| Drywall Nailing | 11/21/2024 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 12/2/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/23/2024 | Not Ready for Inspection | KIRK SANDERS |
| Shower Pan | 12/23/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 12/26/2024 | Not Ready for Inspection | KIRK SANDERS |
| Shower Pan | 12/26/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 1/14/2025 | Approved | KIRK SANDERS |
| Shower Pan | 1/14/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 6/9/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 6/10/2025 | Corrections Issued | KIRK SANDERS |
| Gas Test | 6/12/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 6/12/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/13/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 6/13/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 6/13/2025 | Approved | KIRK SANDERS |
| Final | 6/17/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 6/17/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 6/17/2025 | Approved | KIRK SANDERS |
| Service/Power Release | 6/20/2025 | Approved | MICHAEL PELHAM |
| Final | 7/9/2025 | OK to Issue CofO | KIRK SANDERS |