3548 S REDONDO BLVD 90016
Certificate Information: 3548 S REDONDO BLVD 90016
- Application / Permit
- 22014-10000-05802
- Plan Check / Job No.
- B22LA23851
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: 1st and 2nd floor addtion to (E) ONE STORY GARAGE AND CONVERT TO 2-STORY ADU. See Comment.
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Current Status
- CofO Issued on 10/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | TSE MING HUANG |
| Corrections Issued | 12/5/2022 | TSE MING HUANG |
| Quality Review Completed | 12/6/2022 | EUGENE BARBEAU |
| Plan Check Approved | 4/12/2023 | TSE MING HUANG |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 9/22/2023 | JOSE AVILA |
| Permit Finaled | 10/5/2023 | DEROLD HAUFF |
| CofO Issued | 10/5/2023 | DEROLD HAUFF |
| Permit Finaled | 10/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/6/2023 | AMAAN MALIK |
| Construction near power lines | Cleared | 1/9/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/9/2023 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 3/30/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | , |
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/19/2023 | Approved | STUART CHAPMAN |
| Sewer | 4/19/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 4/19/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/23/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/23/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/23/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 5/23/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/5/2023 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/7/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 6/7/2023 | Approved | JOSE AVILA |
| Insulation | 6/13/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 6/20/2023 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 6/20/2023 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 6/27/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/27/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 9/1/2023 | Approved | JOSE AVILA |
| Final | 9/1/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 9/1/2023 | Approved | JOSE AVILA |
| Service/Power Release | 9/15/2023 | Approved | JOSE AVILA |
| Final | 9/21/2023 | OK to Issue CofO | JOSE AVILA |