2846 N PARTRIDGE AVE 90039
Certificate Information: 2846 N PARTRIDGE AVE 90039
- Application / Permit
- 22014-10000-05796
- Plan Check / Job No.
- B22LA23810
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21' 1 1/2" X 22'-4 3/8" ADDITION, INCLUDING 8'-3" X 4'-0" ATTACHED COVERED PATIO AND REMODEL TO EXISTING SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Current Status
- CofO Issued on 12/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2022 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/5/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 12/29/2022 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 3/30/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 4/6/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 4/12/2023 | MADISON ODELL |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 12/4/2024 | LUIS CASTRO |
| Permit Finaled | 12/5/2024 | DEROLD HAUFF |
| CofO Issued | 12/5/2024 | DEROLD HAUFF |
| Permit Finaled | 12/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/23/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/23/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2022 | AMAAN MALIK |
Contact Information
| Architect | Buangsuwon,, Panupong; Lic. No.: NA18986 | , |
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: NA67603 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 5/31/2023 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/20/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/20/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 6/23/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 8/4/2023 | Approved | DONALD CRICHLOW |
| Deputy Wood Construction | 8/4/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/31/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/25/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/25/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 10/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/5/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 10/10/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/18/2024 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 1/30/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 2/26/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/1/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 11/15/2024 | Corrections Issued | LUIS CASTRO |
| Final | 11/15/2024 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 11/15/2024 | Approved | LUIS CASTRO |
| PLUMBING-Final | 11/15/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 11/19/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 11/19/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 11/19/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 12/3/2024 | OK to Issue CofO | LUIS CASTRO |
| Footing/Foundation/Slab | 12/3/2024 | Approved | LUIS CASTRO |
| MERV13>=Final | 12/3/2024 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 12/3/2024 | Approved | LUIS CASTRO |