3522 S 9TH AVE 90018
Certificate Information: 3522 S 9TH AVE 90018
- Application / Permit
- 22014-10000-05791
- Plan Check / Job No.
- B22LA23800
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/24/2023
- Issuing Office
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2023 | KEVIN MORALES |
| Corrections Issued | 1/4/2023 | KEVIN MORALES |
| Quality Review Completed | 1/6/2023 | EUGENE BARBEAU |
| Plan Check Approved | 2/7/2023 | KEVIN MORALES |
| Issued | 2/24/2023 | APPLICANT |
| CofO in Progress | 11/5/2024 | JUSTIN HAWLEY |
| CofO in Progress | 11/5/2024 | JUSTIN HAWLEY |
| CofO in Progress | 12/30/2024 | JUSTIN HAWLEY |
| CofO in Progress | 12/30/2024 | JUSTIN HAWLEY |
| CofO in Progress | 12/30/2024 | JUSTIN HAWLEY |
| Permit Finaled | 1/2/2025 | DEROLD HAUFF |
| CofO Issued | 1/2/2025 | DEROLD HAUFF |
| Permit Finaled | 1/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | CELINA MORENO |
| Sewer availability | Cleared | 1/12/2023 | CELINA MORENO |
| Low Impact Development | Cleared | 1/24/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/30/2023 | Partial Inspection | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 7/27/2023 | Partial Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 8/22/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 8/29/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 8/30/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 8/31/2023 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 9/7/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/8/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 1/17/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 1/17/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | JUSTIN HAWLEY |
| HVAC-Rough | 1/17/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/17/2024 | Approved | JUSTIN HAWLEY |
| Deputy Wood Construction | 1/29/2024 | Conditional Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/29/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 2/14/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 2/14/2024 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 2/23/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 2/23/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/23/2024 | Approved | JUSTIN HAWLEY |
| Shower Pan | 2/23/2024 | Approved | JUSTIN HAWLEY |
| Sewer | 3/4/2024 | Approved | JUSTIN HAWLEY |
| Final | 5/28/2024 | Corrections Issued | JUSTIN HAWLEY |
| Service/Power Release | 5/28/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 7/24/2024 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 7/24/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Final | 11/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 11/5/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Final | 12/30/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| Service/Power Release | 12/30/2024 | Approved | JUSTIN HAWLEY |