7883 S AIRLANE AVE 90045
Certificate Information: 7883 S AIRLANE AVE 90045
- Application / Permit
- 22014-10000-05788
- Plan Check / Job No.
- B22LA23795
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing 363 sq. ft. garage to new ADU with 270 sq. ft. addition PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Current Status
- CofO Issued on 2/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | VARAND SARKISIAN |
| Corrections Issued | 12/27/2022 | VARAND SARKISIAN |
| Quality Review Completed | 1/5/2023 | HANS SANTIAGO |
| Plan Check Approved | 5/12/2023 | VARAND SARKISIAN |
| Issued | 5/18/2023 | APPLICANT |
| CofO in Progress | 2/23/2024 | BOBBY KEY |
| Permit Finaled | 2/27/2024 | DANIEL ORRANTE |
| CofO Issued | 2/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2022 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 1/5/2023 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 1/12/2023 | CATHERINE ADROVER |
| Sewer availability | Cleared | 1/12/2023 | CATHERINE ADROVER |
| Specific Plan | Cleared | 1/17/2023 | FREDDY GARCIA |
| Construction near power lines | Cleared | 4/27/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/26/2023 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 5/31/2023 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 6/1/2023 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/7/2023 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 6/7/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/23/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/23/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 6/23/2023 | Conditional Approval | BOBBY KEY |
| Underground Mechanical | 6/23/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/25/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 7/25/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 7/25/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 7/25/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 7/25/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 7/25/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 8/3/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/3/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| Green Building Rough | 8/16/2023 | Approved | RICHARD STEINBACH |
| Insulation | 8/16/2023 | Corrections Issued | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/22/2023 | Approved | BOBBY KEY |
| Insulation | 8/22/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/5/2023 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 9/5/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 9/8/2023 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/1/2024 | Corrections Issued | BOBBY KEY |
| Final | 2/1/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 2/1/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 2/1/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 2/1/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 2/1/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/9/2024 | Corrections Issued | BOBBY KEY |
| Final | 2/9/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 2/9/2024 | Approved | BOBBY KEY |
| HVAC-Final | 2/9/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 2/9/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 2/23/2024 | Approved | BOBBY KEY |
| Final | 2/23/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 2/23/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/23/2024 | Approved | BOBBY KEY |