3017 N SILVER LAKE BLVD 1 90039
Certificate Information: 3017 N SILVER LAKE BLVD 1 90039
- Application / Permit
- 22014-10000-05787
- Plan Check / Job No.
- B22LA23794
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 292 S.F. ADDITION (20.25' X 14.6') TO A SINGLE FAMILY RESIDENCE
- Permit Issued
- Issued on 5/4/2023
- Issuing Office
- Current Status
- Issued on 5/4/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2022 | JOHNPAUL ISIP |
| Corrections Issued | 11/30/2022 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 4/18/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 5/4/2023 | JOHNPAUL ISIP |
| Issued | 5/4/2023 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 4/6/2023 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 4/22/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 4/22/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 7/17/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/17/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 7/21/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/26/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/25/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 6/25/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 7/1/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 11/12/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/12/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/20/2024 | Approved | THOMAS LOGRASSO |
| Wood Frame | 12/20/2024 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/29/2025 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 1/29/2025 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 2/13/2025 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 2/13/2025 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 2/13/2025 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/13/2025 | Approved | THOMAS LOGRASSO |
| Shower Pan | 2/13/2025 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/19/2025 | Approved | NICHOLAS LOPEZ |
| MERV13>=Rough | 11/19/2025 | Approved | NICHOLAS LOPEZ |
| Special/Order Compliance | 11/19/2025 | Corrections Issued | NICHOLAS LOPEZ |