4035 S BEETHOVEN ST 90066
Certificate Information: 4035 S BEETHOVEN ST 90066
- Application / Permit
- 22014-10000-05785
- Plan Check / Job No.
- B22LA23791
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO (E) SFD
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | CARLOS MONTES |
| Corrections Issued | 12/4/2022 | CARLOS MONTES |
| Quality Review Completed | 12/6/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/17/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 4/12/2023 | CARLOS MONTES |
| Plan Check Approved | 5/4/2023 | CARLOS MONTES |
| Issued | 5/10/2023 | APPLICANT |
| CofO in Progress | 5/31/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 6/3/2024 | DANIEL ORRANTE |
| CofO Issued | 6/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | JASON NG |
| Sewer availability | Cleared | 4/3/2023 | JASON NG |
| Low Impact Development | Cleared | 4/7/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/24/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: NA87698 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/19/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/20/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 12/7/2023 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 12/7/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 12/7/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 12/18/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 12/18/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/18/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/18/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 12/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 12/22/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 1/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Gas Test | 3/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Sewer | 3/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Gas Test | 3/15/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 3/15/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Service/Power Release | 4/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/10/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/22/2024 | Partial Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 4/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/22/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 4/22/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/24/2024 | Approved | JESUS RODRIGUEZ |
| Final | 5/24/2024 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 5/24/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 5/24/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 5/24/2024 | Approved | JESUS RODRIGUEZ |
| Final | 5/30/2024 | OK to Issue CofO | JESUS RODRIGUEZ |